Food trucks, concession trailers and mobile medical units, used in Washington State are inspected
by the Department of Labor & Industries, Field Services and Public Safety Division and are to be
constructed to comply with the following codes. Copies of the Factory Built Structures WAC
Rules are enclosed. Washington State Amendments and Washington State Building Codes are
available from Washington Association of Building Officials.
1. Rules for Conversion Vendor Units & Medical Units
Chapter 296-150V WAC (Dated 6/21/2016) (Enclosed)
Note: As rules are updated they will be available on our website
http://www.lni.wa.gov/TradesLicensing/FAS/FoodTruckTrailer/default.asp
What codes apply to conversion vendor units or medical units?
(2) A conversion vendor unit or medical unit must comply with the following codes where
applicable:
(a) The International Mechanical Code (current edition), with the amendments made by the
Washington State Building Code Council, chapter 51-52 WAC.
(b)(i) For conversion vending units Article 551, Parts I through VI of National Electrical
Code/National Fire Protection Agency (NFPA) 70, (current edition), or Article 552, Parts I
through V Article of National Electrical Code/National Fire Protection Agency (NFPA) 70,
(current edition),
(ii) For medical units the current edition National Electrical Code as referenced in chapter
19.28 RCW and chapter 296-46B WAC, installing electric wires and equipment.
(c) Chapter 7 of National Fire Protection Association (NFPA) 1192, (current edition), or the
Uniform Plumbing Code (current edition), as adopted and amended according to chapter 19.27
RCW.
(d) The Washington State Building Code Council, chapter 51-50 WAC, International Building
Code (current edition), Chapter 11, Accessibility as applies to the exterior of the unit relating to
customer service facilities in section 1109.11.3
3. Also enclosed for your use are:
A. Concessionaires Letter
B. Vendor/Medical Conversion Units Pre-Inspection Checklist
C. Sample drawing set
D. Plan Approval request form with instructions for completing
E. Application for Insignia form with instructions for completing
Copies of the Codes are available from:
Washington Association of Building Officials
P. O. Box 7310
Olympia, WA 98507-7310
Phone: 360-628-8669
Web Site: wabo.org
You should also contact your local Health Department for their requirements.
STATE OF WASHINGTON
DEPARTMENT OF LABOR AND INDUSTRIES
Field Services & Public Safety
Factory Assembled Structures
PO Box 44430 Olympia, Washington 98504-4430
MEMORANDUM
MANUFACTURER ONLY
TO: Food Truck and Concession Trailer Manufacturer's
FROM: Craig Sedlacek, Plan Review Supervisor
SUBJECT: Manufacturer's Contact Personnel
In order that we may serve you better we are requesting you complete the enclosed form and return it to us.
By having contact persons on our mailing labels and faxes the information we are sending to you should
be received by those who need it. We thank you in advance for your assistance.
If you have any questions, please feel free to contact me at (360)902-5218 or FAX (360)902-5229.
Return to: Craig Sedlacek
Dept. of Labor & Industries
P O Box 44430
Olympia, WA 98504-4430
MANUFACTURER ONLY
Factory 1 Company Name: _________________________________________________
Mailing: Address____________________________________________________
City:_________________________ State: ______ Zip: ______________________
Physical Address: ____________________________________________________
City: ________________________ State: ______ Zip: ______________________
Phone No: (_____) ____________ Ext: ________ Fax No: (____) _____________
Web Address: ______________________________________________________
Contact for Plan Review: ______________________________________________
Phone No: (_____) ____________ Ext: ________ Fax No: (____) ______________
Email Address: ______________________________________________________
Contact for Plant Audit: _______________________________________________
Phone No.: (_____) _____________ Ext: _______ Fax No: (____) _____________
Email Address: ______________________________________________________
Factory # 2 Company Name: ____________________________________________________
(If applicable) Mailing Address:____________________________________________________
City:__________________________ State: ______ Zip: _____________________
Physical Address: ____________________________________________________
City: __________________________ State: ______ Zip: ____________________
Phone No: (_____) ____________ Ext: ________ Fax No: (____) _____________
Web Address: ______________________________________________________
Contact for Plan Review: ______________________________________________
Phone No: (_____) ____________ Ext: ________ Fax No: (____) ______________
Email Address: ______________________________________________________
Contact for Plant Audit: _______________________________________________
Phone No.: (_____) _____________ Ext: _______ Fax No: (____) _____________
Email Address: ______________________________________________________
Chapter 296-150V WACChapter 296-150V WAC
Last Update: 12/4/18Last Update: 12/4/18
Chapter ListingChapter Listing
CONVERSION VENDOR UNITS AND MEDICAL UNITSCONVERSION VENDOR UNITS AND MEDICAL UNITS
WAC SectionsWAC Sections
296-150V-0010296-150V-0010 Authority, purpose, and scope.Authority, purpose, and scope.
296-150V-0020296-150V-0020 What definitions apply to this chapter?What definitions apply to this chapter?
296-150V-0030296-150V-0030 How is this chapter enforced?How is this chapter enforced?
296-150V-0040296-150V-0040 Is manufacturing information kept confidential?Is manufacturing information kept confidential?
296-150V-0050296-150V-0050 Can you prohibit the sale or lease of a conversion vendor unit or medical un
i
Can you prohibit the sale or lease of a conversion vendor unit or medical un
i
296-150V-0060296-150V-0060 Who handles consumer complaints about conversion vendor units or medic
a
Who handles consumer complaints about conversion vendor units or medic
a
296-150V-0070296-150V-0070 Do you have reciprocal agreements with other states to inspect conversion
v
Do you have reciprocal agreements with other states to inspect conversion
v
medical units?medical units?
296-150V-0080296-150V-0080 Do you allow a local enforcement agency to inspect conversion vendor unit
s
Do you allow a local enforcement agency to inspect conversion vendor unit
s
the manufacturing location?the manufacturing location?
296-150V-0100296-150V-0100 What happens if I disagree with your decision regarding my compliance wit
h
What happens if I disagree with your decision regarding my compliance wit
h
296-150V-0110296-150V-0110 Do you have an advisory board to address conversion vendor unit and mediDo you have an advisory board to address conversion vendor unit and medi
296-150V-0120296-150V-0120 Where can I obtain technical assistance regarding conversion vendor units
o
Where can I obtain technical assistance regarding conversion vendor units
o
296-150V-0140296-150V-0140 Do you allow the use of alternate materials, design, or method of constructi
o
Do you allow the use of alternate materials, design, or method of constructi
o
296-150V-0200296-150V-0200 Who must obtain conversion vendor unit or medical unit insignia?Who must obtain conversion vendor unit or medical unit insignia?
296-150V-0210296-150V-0210 What are the insignia requirements?What are the insignia requirements?
296-150V-0220296-150V-0220 How do I obtain insignia information and the required forms?How do I obtain insignia information and the required forms?
296-150V-0230296-150V-0230 What are the insignia application requirements?What are the insignia application requirements?
296-150V-0240296-150V-0240 What documentation do you need to perform an alteration inspection?What documentation do you need to perform an alteration inspection?
296-150V-0250296-150V-0250 How do I replace lost or damaged insignia?How do I replace lost or damaged insignia?
296-150V-0300296-150V-0300 When is design-plan approval required?When is design-plan approval required?
296-150V-0310296-150V-0310 Who can approve design plans?Who can approve design plans?
296-150V-0320296-150V-0320 What must I provide with my request for conversion vendor unit or medical
u
What must I provide with my request for conversion vendor unit or medical
u
approval by the department?approval by the department?
296-150V-0340296-150V-0340 When is an engineering analysis or structural load test for design plans req
u
When is an engineering analysis or structural load test for design plans req
u
296-150V-0350296-150V-0350 What must test procedures and results for design plans include?What must test procedures and results for design plans include?
296-150V-0380296-150V-0380 What happens if you approve my design plan?What happens if you approve my design plan?
296-150V-0390296-150V-0390 If my design plan is not approved, how much time do I have to submit a corrIf my design plan is not approved, how much time do I have to submit a corr
296-150V-0400296-150V-0400 What happens after my design plan is approved?What happens after my design plan is approved?
296-150V-0410296-150V-0410 When does my design plan expire?When does my design plan expire?
296-150V-0415296-150V-0415 Who approves addendums to design plans?Who approves addendums to design plans?
296-150V-0495296-150V-0495 Contractor deposit accounts.Contractor deposit accounts.
Page 1 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0500296-150V-0500 When is an inspection required?When is an inspection required?
296-150V-0510296-150V-0510 How do I request an inspection?How do I request an inspection?
296-150V-0520296-150V-0520 What happens if my conversion vendor unit or medical unit passes inspecti
o
What happens if my conversion vendor unit or medical unit passes inspecti
o
296-150V-0530296-150V-0530 Am I charged if I request an inspection but I am not prepared?Am I charged if I request an inspection but I am not prepared?
296-150V-0540296-150V-0540 Who inspects a conversion vendor unit or medical unit installation at the builWho inspects a conversion vendor unit or medical unit installation at the buil
location?location?
296-150V-0550296-150V-0550 Do you allow a conversion vendor unit or medical unit to be completed at th
e
Do you allow a conversion vendor unit or medical unit to be completed at th
e
296-150V-0560296-150V-0560 What happens if I receive a notice of noncompliance after inspection of the
a
What happens if I receive a notice of noncompliance after inspection of the
a
conversion vendor unit or medical unit?conversion vendor unit or medical unit?
296-150V-0580296-150V-0580 Must I obtain an insignia for used conversion vendor units or medical units?Must I obtain an insignia for used conversion vendor units or medical units?
296-150V-0590296-150V-0590 How do I obtain insignia for used conversion vendor units or medical units?How do I obtain insignia for used conversion vendor units or medical units?
296-150V-0700296-150V-0700 Must manufacturers of conversion vendor units and medical units notify you Must manufacturers of conversion vendor units and medical units notify you
more than one location?more than one location?
296-150V-0710296-150V-0710 Must manufacturers of conversion vendor units and medical units notify you Must manufacturers of conversion vendor units and medical units notify you
business name or address?business name or address?
296-150V-0720296-150V-0720 Must manufacturers of conversion vendor units and medical units notify you Must manufacturers of conversion vendor units and medical units notify you
business ownership?business ownership?
296-150V-0800296-150V-0800 What codes apply to conversion vendor units or medical units?What codes apply to conversion vendor units or medical units?
296-150V-0930296-150V-0930 When are structural load tests or structural calculations required?When are structural load tests or structural calculations required?
296-150V-0950296-150V-0950 What requirements apply to roof coverings?What requirements apply to roof coverings?
296-150V-1040296-150V-1040 Are there floor requirements?Are there floor requirements?
296-150V-1070296-150V-1070 What requirements apply to floor closure material?What requirements apply to floor closure material?
296-150V-1090296-150V-1090 What are the standards for equipment and installations?What are the standards for equipment and installations?
296-150V-1100296-150V-1100 What are the flame-spread limitations?What are the flame-spread limitations?
296-150V-1110296-150V-1110 Combustible limitations.Combustible limitations.
296-150V-1120296-150V-1120 What are the standards for wall and cabinet protection?What are the standards for wall and cabinet protection?
296-150V-1170296-150V-1170 What are the light and ventilation requirements?What are the light and ventilation requirements?
296-150V-1180296-150V-1180 What requirements apply to conversion vendor unit exits?What requirements apply to conversion vendor unit exits?
296-150V-1185296-150V-1185 What exit door requirements apply to self-propelled medical unit exits?What exit door requirements apply to self-propelled medical unit exits?
296-150V-1190296-150V-1190 Interior privacy locks.Interior privacy locks.
296-150V-1303296-150V-1303 How must storage batteries be installed in a conversion vendor unit or medi
c
How must storage batteries be installed in a conversion vendor unit or medi
c
296-150V-1330296-150V-1330 What are the mechanical requirements for a conversion vendor unit or medi
c
What are the mechanical requirements for a conversion vendor unit or medi
c
296-150V-1350296-150V-1350 What are the LPG system enclosure and mounting requirements for a conv
e
What are the LPG system enclosure and mounting requirements for a conv
e
medical unit?medical unit?
296-150V-1360296-150V-1360 What are the fuel gas piping design requirements for a conversion vendor u
n
What are the fuel gas piping design requirements for a conversion vendor u
n
296-150V-1380296-150V-1380 Can gas tubing be concealed in a conversion vendor unit or medical unit?Can gas tubing be concealed in a conversion vendor unit or medical unit?
296-150V-1390296-150V-1390 What are the pipe-joint compound requirements for gas piping in a conversi
o
What are the pipe-joint compound requirements for gas piping in a conversi
o
medical unit?medical unit?
296-150V-1400296-150V-1400 What are the gas piping hanger and support requirements for a conversion
v
What are the gas piping hanger and support requirements for a conversion
v
unit?unit?
296-150V-1410296-150V-1410
Page 2 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
What are the electrical bonding requirements for gas piping in a conversion
v
What are the electrical bonding requirements for gas piping in a conversion
v
unit?unit?
296-150V-1420296-150V-1420 How are gas supply connections in a conversion vendor unit or medical unit How are gas supply connections in a conversion vendor unit or medical unit
296-150V-1430296-150V-1430 What requirements apply to gas piping system openings?What requirements apply to gas piping system openings?
296-150V-1440296-150V-1440
A
re gas piping shut-off valves required in a conversion vendor unit or medic
aA
re gas piping shut-off valves required in a conversion vendor unit or medic
a
296-150V-1450296-150V-1450 What requirements apply to testing for gas piping leaks before conversion v
e
What requirements apply to testing for gas piping leaks before conversion v
e
unit appliances are connected?unit appliances are connected?
296-150V-1460296-150V-1460 What requirements apply to testing for gas piping leaks after conversion ve
n
What requirements apply to testing for gas piping leaks after conversion ve
n
appliances are connected?appliances are connected?
296-150V-1470296-150V-1470 What are the requirements for appliance installations?What are the requirements for appliance installations?
296-150V-1530296-150V-1530 What general plumbing requirements apply?What general plumbing requirements apply?
296-150V-1540296-150V-1540 What are the plumbing definitions?What are the plumbing definitions?
296-150V-1550296-150V-1550 What requirements apply to drain outlets?What requirements apply to drain outlets?
296-150V-1560296-150V-1560 What is the minimum clearance for drain outlets?What is the minimum clearance for drain outlets?
296-150V-1570296-150V-1570 What requirements apply to water-supply connections?What requirements apply to water-supply connections?
296-150V-1580296-150V-1580 What requirements apply to water heater relief valves and safety devices?What requirements apply to water heater relief valves and safety devices?
296-150V-1590296-150V-1590 What requirements apply to waste holding tanks for conversion vendor unitsWhat requirements apply to waste holding tanks for conversion vendor units
296-150V-1600296-150V-1600 What are the requirements associated with medical and conversion vending What are the requirements associated with medical and conversion vending
manufactured and used outside the state according to RCW manufactured and used outside the state according to RCW 43.22.38043.22.380 ??
296-150V-3000296-150V-3000 Conversion vendor units and medical units—Fees.Conversion vendor units and medical units—Fees.
DISPOSITION OF SECTIONS FORMERLY CODIFIED IN THIS TITL
E
DISPOSITION OF SECTIONS FORMERLY CODIFIED IN THIS TITL
E
296-150V-0205296-150V-0205 Can I obtain an exempt vendor/medical insignia? [Statutory Authority: Chapt
e
Can I obtain an exempt vendor/medical insignia? [Statutory Authority: Chapt
e
2003 c 291. WSR 05-01-102, § 296-150V-0205, filed 12/14/04, effective 2/1/
0
2003 c 291. WSR 05-01-102, § 296-150V-0205, filed 12/14/04, effective 2/1/
0
16-13-119, filed 6/21/16, effective 6/21/16. Statutory Authority: Chapter 16-13-119, filed 6/21/16, effective 6/21/16. Statutory Authority: Chapter 43.2243.22
296-150V-1220296-150V-1220 What code and installation requirements apply to conversion vendor unit or
m
What code and installation requirements apply to conversion vendor unit or
m
systems? [Statutory Authority: RCW systems? [Statutory Authority: RCW 43.22.34043.22.340 , , 43.22.35043.22.350 , , 43.22.35543.22.355 , , 43.
2
43.
2
43.22.43243.22.432 , , 43.22.43343.22.433 , , 43.22.43443.22.434 , , 43.22.45043.22.450 , , 43.22.48043.22.480 , and , and 43.22.48543.22.485 .
W
.
W
296-150V-1220, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter 296-150V-1220, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter
44
18-069, § 296-150V-1220, filed 8/31/99, effective 10/1/99.] Repealed by WS
R
18-069, § 296-150V-1220, filed 8/31/99, effective 10/1/99.] Repealed by WS
R
5/30/03, effective 6/30/03. Statutory Authority: RCW 5/30/03, effective 6/30/03. Statutory Authority: RCW 43.22.34043.22.340 , , 43.22.40043.22.400 , ,
44
43.22.43443.22.434 , , 43.22.48043.22.480 , and , and 43.22.48543.22.485 , 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RC
W
RC
W
296-150V-0010296-150V-0010
Authority, purpose, and scope.Authority, purpose, and scope.
(1) This chapter is authorized by RCW (1) This chapter is authorized by RCW 43.22.34043.22.340 through through 43.22.43443.22.434 covering the covering the
construction, alteration, and approval of conversion vendor units and medical units sold, construction, alteration, and approval of conversion vendor units and medical units sold,
leased, or used in Washington state.leased, or used in Washington state.
(2) This chapter applies to the approval of conversion vendor unit and medical unit (2) This chapter applies to the approval of conversion vendor unit and medical unit
manufacturers, dealers, and to any person who manufactures or alters the plumbing, manufacturers, dealers, and to any person who manufactures or alters the plumbing,
mechanical, or electrical system of a conversion vendor unit or medical unit.mechanical, or electrical system of a conversion vendor unit or medical unit.
Page 3 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0010, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0010, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0020296-150V-0020
What definitions apply to this chapter?What definitions apply to this chapter?
"Alteration""Alteration" is the replacement, addition, modification, or removal of any equipment or is the replacement, addition, modification, or removal of any equipment or
installation that affects the construction for concentrated floor loads, fire and life safety, or the installation that affects the construction for concentrated floor loads, fire and life safety, or the
plumbing, mechanical, and electrical systems of a conversion vendor unit or medical unit.plumbing, mechanical, and electrical systems of a conversion vendor unit or medical unit.
The following are not considered alterations:The following are not considered alterations:
• Repairs with approved parts;• Repairs with approved parts;
• Modifications of a fuel-burning appliance according to the listing agency's • Modifications of a fuel-burning appliance according to the listing agency's
specifications; orspecifications; or
• Adjustment and maintenance of equipment.• Adjustment and maintenance of equipment.
"Approved""Approved" is approved by the department of labor and industries.is approved by the department of labor and industries.
"Consumer""Consumer" is a person or organization, excluding a manufacturer or dealer of is a person or organization, excluding a manufacturer or dealer of
conversion vendor units or medical units, who buys or leases a conversion vendor unit or conversion vendor units or medical units, who buys or leases a conversion vendor unit or
medical unit.medical unit.
"Conversion vendor unit""Conversion vendor unit"or or "Conversion vending unit""Conversion vending unit" means a motor vehicle or means a motor vehicle or
other structure that has been converted or built for the purpose of being used for commercial other structure that has been converted or built for the purpose of being used for commercial
sales at temporary locations. The units must be 8 feet 6 inches or less in width (exterior floor sales at temporary locations. The units must be 8 feet 6 inches or less in width (exterior floor
measurement) in the set-up position, and the inside working area must be less than 40 feet in measurement) in the set-up position, and the inside working area must be less than 40 feet in
length (interior floor measurement). Conversion vendor units:length (interior floor measurement). Conversion vendor units:
• Are transported in only one section;• Are transported in only one section;
• Are designed for highway use;• Are designed for highway use;
• Are temporarily occupied for distribution of items, e.g., food;• Are temporarily occupied for distribution of items, e.g., food;
• Are built on a permanent chassis; and• Are built on a permanent chassis; and
• Include at least one of the following systems: Plumbing, mechanical or 120 and/or • Include at least one of the following systems: Plumbing, mechanical or 120 and/or
240 volt electrical.240 volt electrical.
Note
:
Note
:
The conversion vendor unit may The conversion vendor unit may NOTNOT include a dining area.include a dining area.
"Damaged in transit""Damaged in transit" means damage that affects the integrity of a concentrated floor means damage that affects the integrity of a concentrated floor
load design or any of the systems.load design or any of the systems.
"Dealer""Dealer" is a person, company, or corporation whose business is leasing, selling, is a person, company, or corporation whose business is leasing, selling,
offering for lease or sale, buying, or trading conversion vendor units, or medical units.offering for lease or sale, buying, or trading conversion vendor units, or medical units.
"Department""Department" is the department of labor and industries. The department may be is the department of labor and industries. The department may be
referred to as "we" or "us" in this chapter. Note: You may contact us at: Department of Labor referred to as "we" or "us" in this chapter. Note: You may contact us at: Department of Labor
and Industries, Specialty Compliance, P.O. Box 44440, Olympia, WA 98504-4440.and Industries, Specialty Compliance, P.O. Box 44440, Olympia, WA 98504-4440.
"Design plan""Design plan" is a plan for the construction or alteration of a conversion vendor unit or is a plan for the construction or alteration of a conversion vendor unit or
medical unit or conversion of a vehicle to a conversion vendor unit or medical unit including medical unit or conversion of a vehicle to a conversion vendor unit or medical unit including
floor plans, specifications, or test results necessary for a complete evaluation of the design, if floor plans, specifications, or test results necessary for a complete evaluation of the design, if
applicable.applicable.
"Design option""Design option" is a design that a manufacturer may use as an option to its is a design that a manufacturer may use as an option to its
conversion vendor unit or medical unit design plan.conversion vendor unit or medical unit design plan.
"Educational facility""Educational facility" is a building or portion of a building used primarily for is a building or portion of a building used primarily for
educational purposes by six or more persons at one time for twelve hours per week or four educational purposes by six or more persons at one time for twelve hours per week or four
Page 4 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
hours in any one day. Educational occupancy includes: Schools (preschool through grade hours in any one day. Educational occupancy includes: Schools (preschool through grade
twelve), colleges, academies, universities, and trade schools.twelve), colleges, academies, universities, and trade schools.
"Equipment""Equipment" is all material, appliances, devices, fixtures, fittings, or accessories used is all material, appliances, devices, fixtures, fittings, or accessories used
in the manufacture, assembly, conversion to, or alteration of a conversion vendor unit or in the manufacture, assembly, conversion to, or alteration of a conversion vendor unit or
medical unit.medical unit.
"Factory assembled structure (FAS) advisory board""Factory assembled structure (FAS) advisory board" is a board authorized to is a board authorized to
advise the director of the department regarding the issues and adoption of rules relating to advise the director of the department regarding the issues and adoption of rules relating to
conversion vendor units and medical units.conversion vendor units and medical units.
"Health or personal care facilities""Health or personal care facilities" are buildings or parts of buildings that contain, are buildings or parts of buildings that contain,
but are not limited to, facilities that are required to be licensed by the department of social and but are not limited to, facilities that are required to be licensed by the department of social and
health services or the department of health (e.g., hospitals, nursing homes, private alcoholism health services or the department of health (e.g., hospitals, nursing homes, private alcoholism
hospitals, private psychiatric hospitals, boarding homes, alcoholism treatment facilities, hospitals, private psychiatric hospitals, boarding homes, alcoholism treatment facilities,
maternity homes, birth centers or childbirth centers, residential treatment facilities for maternity homes, birth centers or childbirth centers, residential treatment facilities for
psychiatrically impaired children and youths, and renal hemodialysis clinics) and medical, psychiatrically impaired children and youths, and renal hemodialysis clinics) and medical,
dental or chiropractic offices or clinics, outpatient or ambulatory surgical clinics, and such dental or chiropractic offices or clinics, outpatient or ambulatory surgical clinics, and such
other health care occupancies where patients who may be unable to provide for their own other health care occupancies where patients who may be unable to provide for their own
needs and safety without the assistance of another person are treated. (Further defined in needs and safety without the assistance of another person are treated. (Further defined in
WAC WAC 296-46B-010296-46B-010.).)
"Insignia""Insignia" is a label that we attach to a conversion vendor unit or medical unit to verify is a label that we attach to a conversion vendor unit or medical unit to verify
that the structure meets the requirements of this chapter and the applicable codes.that the structure meets the requirements of this chapter and the applicable codes.
"Install""Install" is to erect, construct, assemble, or set a conversion vendor unit or medical is to erect, construct, assemble, or set a conversion vendor unit or medical
unit in place.unit in place.
"Institutional facility""Institutional facility" is a building or portion of a building used primarily for detention is a building or portion of a building used primarily for detention
and correctional occupancies where some degree of restraint or security is required for a time and correctional occupancies where some degree of restraint or security is required for a time
period of twenty-four or more hours. Such occupancies include, but are not restricted to: Penal period of twenty-four or more hours. Such occupancies include, but are not restricted to: Penal
institutions, reformatories, jails, detention centers, correcti
onal centers, and residential-institutions, reformatories, jails, detention centers, correctional centers, and residential-
restrained care.restrained care.
"Labeled""Labeled" is to bear the department's insignia.is to bear the department's insignia.
"Listed""Listed" is a piece of equipment or apparatus that has been approved by a testing is a piece of equipment or apparatus that has been approved by a testing
agency to the appropriate standard.agency to the appropriate standard.
"Local enforcement agency""Local enforcement agency" is an agency of city or county government with power is an agency of city or county government with power
to enforce local regulations governing the installation of a conversion vendor unit or medical to enforce local regulations governing the installation of a conversion vendor unit or medical
unit.unit.
"Medical unit""Medical unit" is a type of self-propelled unit used to provide medical examinations, is a type of self-propelled unit used to provide medical examinations,
treatments, and medical and dental services or procedures, not including emergency treatments, and medical and dental services or procedures, not including emergency
response vehicles, and which:response vehicles, and which:
• Is transportable;• Is transportable;
• Is temporarily placed and used;• Is temporarily placed and used;
• Is built on a permanent chassis;• Is built on a permanent chassis;
• Includes at least one system;• Includes at least one system;
• Is for temporary use only.• Is for temporary use only.
"One-year design plan""One-year design plan" is a design plan that expires one year after approval or when is a design plan that expires one year after approval or when
a new state building code has been adopted.a new state building code has been adopted.
"System""System" is part of a conversion vendor unit or medical unit designed to serve a is part of a conversion vendor unit or medical unit designed to serve a
particular function. Examples include plumbing, electrical, or mechanical systems.particular function. Examples include plumbing, electrical, or mechanical systems.
Page 5 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0020, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0020, filed 6/21/16,
effective 6/21/16; WSR 05-23-002, § 296-150V-0020, filed 11/3/05, effective 12/4/05. effective 6/21/16; WSR 05-23-002, § 296-150V-0020, filed 11/3/05, effective 12/4/05.
Statutory Authority: RCW Statutory Authority: RCW 43.22.34043.22.340, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.48043.22.480, ,
and and 43.22.48543.22.485, 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RCW. WSR 03-12-044, § 296-150V-0020, filed RCW. WSR 03-12-044, § 296-150V-0020, filed
5/30/03, effective 6/30/03. Statutory Authority: Chapter 5/30/03, effective 6/30/03. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-RCW. WSR 99-18-069, § 296-
150V-0020, filed 8/31/99, effective 10/1/99.]150V-0020, filed 8/31/99, effective 10/1/99.]
296-150V-0030296-150V-0030
How is this chapter enforced?How is this chapter enforced?
(1) To enforce this chapter, we or another governmental inspection agency will inspect (1) To enforce this chapter, we or another governmental inspection agency will inspect
each conversion vendor unit or medical unit manufactured, sold, leased, or used in each conversion vendor unit or medical unit manufactured, sold, leased, or used in
Washington state as required by this chapter.Washington state as required by this chapter.
(2) We will inspect all alterations.(2) We will inspect all alterations.
(3) We will conduct inspections during normal work hours or at other reasonable times.(3) We will conduct inspections during normal work hours or at other reasonable times.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0030, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0030, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0040296-150V-0040
Is manufacturing information kept confidential?Is manufacturing information kept confidential?
We will only release manufacturing information such as design plans, specifications, We will only release manufacturing information such as design plans, specifications,
and test results according to the requirements of the Public Records Act (see RCW and test results according to the requirements of the Public Records Act (see RCW 42.17.31042.17.310
(1)(h)) unless we are ordered to do so by a court or otherwise required by law.(1)(h)) unless we are ordered to do so by a court or otherwise required by law.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0040, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0040, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0050296-150V-0050
Can you prohibit the sale or lease of a conversion vendor unit or medical Can you prohibit the sale or lease of a conversion vendor unit or medical
unit?unit?
(1) We may prohibit the sale or lease of your conversion vendor unit or medical unit (1) We may prohibit the sale or lease of your conversion vendor unit or medical unit
because it is unlawful for any person to sell, lease, or offer for sale a conversion vendor unit or because it is unlawful for any person to sell, lease, or offer for sale a conversion vendor unit or
medical unit within this state if it violates any of the requirements of this chapter.medical unit within this state if it violates any of the requirements of this chapter.
(2) If an inspection reveals that a conversion vendor unit or medical unit violates this (2) If an inspection reveals that a conversion vendor unit or medical unit violates this
chapter, we may post a notice prohibiting the sale or lease of a conversion vendor unit or chapter, we may post a notice prohibiting the sale or lease of a conversion vendor unit or
medical unit.medical unit.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0050, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0050, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 6 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0060296-150V-0060
Who handles consumer complaints about conversion vendor units or Who handles consumer complaints about conversion vendor units or
medical units?medical units?
(1) Consumers may file complaints within one year of the date of manufacture.(1) Consumers may file complaints within one year of the date of manufacture.
(2) The complaint should be in writing and describe the item(s) that may not comply (2) The complaint should be in writing and describe the item(s) that may not comply
with this chapter.with this chapter.
(3) After we receive the complaint, we will send the manufacturer and the dealer a (3) After we receive the complaint, we will send the manufacturer and the dealer a
copy of the complaint.copy of the complaint.
(4) The manufacturer and/or dealer have thirty days to respond. We will base our (4) The manufacturer and/or dealer have thirty days to respond. We will base our
actions on the response.actions on the response.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0060, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0060, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0070296-150V-0070
Do you have reciprocal agreements with other states to inspect Do you have reciprocal agreements with other states to inspect
conversion vendor units and medical units?conversion vendor units and medical units?
(1) We will enter into reciprocal agreements with states that have inspection standards (1) We will enter into reciprocal agreements with states that have inspection standards
equal or greater than our standard.equal or greater than our standard.
(2) When we have a reciprocal agreement with another state:(2) When we have a reciprocal agreement with another state:
(a) The reciprocal state inspects the conversion vendor units and medical units (a) The reciprocal state inspects the conversion vendor units and medical units
manufactured in that state before shipment into Washington to ensure compliance with our manufactured in that state before shipment into Washington to ensure compliance with our
laws. After inspection, the reciprocal state applies our insignia.laws. After inspection, the reciprocal state applies our insignia.
(b) The department inspects conversion vendor units and medical units manufactured (b) The department inspects conversion vendor units and medical units manufactured
in Washington before shipment into the reciprocal state to ensure compliance with their laws. in Washington before shipment into the reciprocal state to ensure compliance with their laws.
After inspection, we apply the insignia of the reciprocal state.After inspection, we apply the insignia of the reciprocal state.
(3) We have reciprocal agreements on file.(3) We have reciprocal agreements on file.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0070, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0070, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0080296-150V-0080
Do you allow a local enforcement agency to inspect conversion vendor Do you allow a local enforcement agency to inspect conversion vendor
units and medical units at the manufacturing location?units and medical units at the manufacturing location?
(1) A local enforcement agency (city or county), under contract with us, can inspect (1) A local enforcement agency (city or county), under contract with us, can inspect
conversion vendor units and medical units. In some cases, another agency's contracts may be conversion vendor units and medical units. In some cases, another agency's contracts may be
limited to specific portions of an inspection at specified manufacturing locations.limited to specific portions of an inspection at specified manufacturing locations.
Page 7 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(2) After approving a unit, the local enforcement agency will attach the insignia which (2) After approving a unit, the local enforcement agency will attach the insignia which
indicates that the unit has passed inspection.indicates that the unit has passed inspection.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0080, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0080, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0100296-150V-0100
What happens if I disagree with your decision regarding my compliance What happens if I disagree with your decision regarding my compliance
with this chapter?with this chapter?
(1) If we determine that you are in violation of this chapter, you will receive a notice of (1) If we determine that you are in violation of this chapter, you will receive a notice of
noncompliance.noncompliance.
(2) If you disagree with our decision, you can send us a written request for a hearing, (2) If you disagree with our decision, you can send us a written request for a hearing,
stating why you disagree.stating why you disagree.
(3) After we receive your hearing request, we will:(3) After we receive your hearing request, we will:
(a) Schedule a hearing within thirty days after we receive your request;(a) Schedule a hearing within thirty days after we receive your request;
(b) Notify you of the time, date, and place for the hearing. If you fail to appear, your (b) Notify you of the time, date, and place for the hearing. If you fail to appear, your
case will be dismissed;case will be dismissed;
(c) Hear your case;(c) Hear your case;
(d) Send written notice of our decision to you.(d) Send written notice of our decision to you.
(4) If you disagree with our decision, you may appeal it under the Administrative (4) If you disagree with our decision, you may appeal it under the Administrative
Procedure Act, chapter Procedure Act, chapter 34.0534.05 RCW.RCW.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0100, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0100, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0110296-150V-0110
Do you have an advisory board to address conversion vendor unit and Do you have an advisory board to address conversion vendor unit and
medical unit issues?medical unit issues?
The factory assembled structures (FAS) board advises us on issues relating to The factory assembled structures (FAS) board advises us on issues relating to
plumbing, mechanical, electrical, inspections, and rule adoption for conversion vendor units plumbing, mechanical, electrical, inspections, and rule adoption for conversion vendor units
and medical units. (See RCW and medical units. (See RCW 43.22.42043.22.420.).)
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0110, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0110, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0120296-150V-0120
Where can I obtain technical assistance regarding conversion vendor units Where can I obtain technical assistance regarding conversion vendor units
or medical units?or medical units?
Page 8 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
We offer field technical service to conversion vendor unit and medical unit We offer field technical service to conversion vendor unit and medical unit
manufacturers for an hourly fee. (See WAC manufacturers for an hourly fee. (See WAC 296-150V-3000296-150V-3000.) Field technical service may .) Field technical service may
include evaluation, consultation, plan examination, interpretation, and clarification of technical include evaluation, consultation, plan examination, interpretation, and clarification of technical
data relating to the application of our rules. It does not include inspections.data relating to the application of our rules. It does not include inspections.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0120, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0120, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0140296-150V-0140
Do you allow the use of alternate materials, design, or method of Do you allow the use of alternate materials, design, or method of
construction?construction?
An applicant may apply for the use of alternate materials, design, or methods of An applicant may apply for the use of alternate materials, design, or methods of
construction different from the requirements of this chapter by filing a written request with the construction different from the requirements of this chapter by filing a written request with the
department.department.
(1) (1) Responsibilities of the applicant.Responsibilities of the applicant. The applicant must submit in writing the The applicant must submit in writing the
following information:following information:
(a) Name, address, and phone number;(a) Name, address, and phone number;
(b) The specific requirement or requirements from which the alternate material, design, (b) The specific requirement or requirements from which the alternate material, design,
or method of construction is requested;or method of construction is requested;
(c) Justification that the requirements of this chapter cannot be met without using (c) Justification that the requirements of this chapter cannot be met without using
alternate materials, design, or method of construction;alternate materials, design, or method of construction;
(d) How the use of alternate materials, design, or method of construction will achieve (d) How the use of alternate materials, design, or method of construction will achieve
the same result as the requirement and any specific alternative measures to be taken to show the same result as the requirement and any specific alternative measures to be taken to show
the alternate provides the same level of protection to life, safety and health as the the alternate provides the same level of protection to life, safety and health as the
requirements;requirements;
The department has a form that you may use for your request. Please contact us at The department has a form that you may use for your request. Please contact us at
the address shown in WAC the address shown in WAC 296-150V-0020296-150V-0020, Definitions., Definitions.
(2) (2) Responsibilities of the department.Responsibilities of the department. The department will provide a written The department will provide a written
response to the applicant within thirty days of receipt of the written request. The written response to the applicant within thirty days of receipt of the written request. The written
response will state the acceptance or denial of the request, including the reasons for the response will state the acceptance or denial of the request, including the reasons for the
department's decision. At a minimum the department will base its decision on:department's decision. At a minimum the department will base its decision on:
(a) The applicant's request as described in subsection (1) of this section;(a) The applicant's request as described in subsection (1) of this section;
(b) Research into the request;(b) Research into the request;
(c) Expert advice.(c) Expert advice.
(3) (3) Applicant's response to denials.Applicant's response to denials. The applicant may appeal the department's The applicant may appeal the department's
decision by following the procedure in WAC decision by following the procedure in WAC 296-150V-0100296-150V-0100..
[Statutory Authority: RCW [Statutory Authority: RCW 43.22.34043.22.340, , 43.22.35043.22.350, , 43.22.35543.22.355, , 43.22.36043.22.360, , 43.22.40043.22.400, , 43.22.432
43.22.432, ,
43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.45043.22.450, , 43.22.48043.22.480, and , and 43.22.48543.22.485. WSR 00-17-148, § 296-150V-. WSR 00-17-148, § 296-150V-
0140, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter 0140, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-RCW. WSR 99-18-
069, § 296-150V-0140, filed 8/31/99, effective 10/1/99.]069, § 296-150V-0140, filed 8/31/99, effective 10/1/99.]
Page 9 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0200296-150V-0200
Who must obtain conversion vendor unit or medical unit insignia?Who must obtain conversion vendor unit or medical unit insignia?
(1) You must obtain an insignia from us for each conversion vendor unit or medical unit (1) You must obtain an insignia from us for each conversion vendor unit or medical unit
manufactured, sold, leased, or used in Washington state.manufactured, sold, leased, or used in Washington state.
(2) You do not need an insignia for a conversion vendor unit or medical unit if a unit (2) You do not need an insignia for a conversion vendor unit or medical unit if a unit
was manufactured prior to July 1, 1968. (See RCW was manufactured prior to July 1, 1968. (See RCW 43.22.37043.22.370.).)
(3) You must obtain an insignia when conversion vendor units or medical units are (3) You must obtain an insignia when conversion vendor units or medical units are
altered in Washington state.altered in Washington state.
(4) You must obtain an alteration insignia when a conversion vendor unit or medical (4) You must obtain an alteration insignia when a conversion vendor unit or medical
unit is damaged in transit after leaving the manufacturing location or during an on-site unit is damaged in transit after leaving the manufacturing location or during an on-site
installation and an alteration or repair is necessary. The insignia indicates the conversion installation and an alteration or repair is necessary. The insignia indicates the conversion
vendor unit or medical unit was altered or repaired.vendor unit or medical unit was altered or repaired.
(5) You must have an approved design plan and pass our inspection before we will (5) You must have an approved design plan and pass our inspection before we will
attach an insignia.attach an insignia.
Note
:
Note
:
A
ll conversion vendor units and medical units must have insignia if they are altered; this includes the exceptions in
A
ll conversion vendor units and medical units must have insignia if they are altered; this includes the exceptions in
subsection (2)(a) and (b) of this section
.
subsection (2)(a) and (b) of this section
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0200, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0200, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0200, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0200, filed 8/31/99, effective 10/1/99.]
296-150V-0210296-150V-0210
What are the insignia requirements?What are the insignia requirements?
(1) If you are applying for insignia, you must have your design plan approved when (1) If you are applying for insignia, you must have your design plan approved when
required by WAC required by WAC 296-150V-0300296-150V-0300 and your conversion vendor unit or medical unit inspected and your conversion vendor unit or medical unit inspected
and approved by us.and approved by us.
(2) If you are a manufacturer, dealer, or owner applying for an alteration insignia, your (2) If you are a manufacturer, dealer, or owner applying for an alteration insignia, your
alteration must be inspected and approved by us. Approval of the design plan may also be alteration must be inspected and approved by us. Approval of the design plan may also be
required.required.
(3) We will attach the insignia to your conversion vendor unit or medical unit after:(3) We will attach the insignia to your conversion vendor unit or medical unit after:
(a) We receive from you the required forms and fees listed in WAC (a) We receive from you the required forms and fees listed in WAC 296-150V-3000296-150V-3000; ;
andand
(b) Your conversion vendor unit or medical unit has passed final inspection.(b) Your conversion vendor unit or medical unit has passed final inspection.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0210, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0210, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0210, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0210, filed 8/31/99, effective 10/1/99.]
296-150V-0220296-150V-0220
How do I obtain insignia information and the required forms?How do I obtain insignia information and the required forms?
Upon request, we will provide you with a packet of information that includes the Upon request, we will provide you with a packet of information that includes the
required forms. Our address is noted in the definition of "department" in WAC required forms. Our address is noted in the definition of "department" in WAC 296-150V-0020296-150V-0020..
Page 10 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0220, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0220, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0230296-150V-0230
What are the insignia application requirements?What are the insignia application requirements?
(1) If you are requesting insignia for conversion vendor units or medical units your (1) If you are requesting insignia for conversion vendor units or medical units your
completed application must include:completed application must include:
(a) A completed design plan approval request form when required by WAC (a) A completed design plan approval request form when required by WAC 296-150V-296-150V-
03000300;;
(b) When required by WAC (b) When required by WAC 296-150V-0300296-150V-0300, one complete set of design plans, , one complete set of design plans,
specifications, engineering analysis and test procedures and results (when applicable), plus specifications, engineering analysis and test procedures and results (when applicable), plus
one additional set for each manufacturing location where the design plan will be used;one additional set for each manufacturing location where the design plan will be used;
(c) For medical units at least one set of design plans must have an original wet stamp (c) For medical units at least one set of design plans must have an original wet stamp
from a professional engineer or architect licensed in Washington state. For conversion vendor from a professional engineer or architect licensed in Washington state. For conversion vendor
units a professional engineer or architect stamp is only required on the structural load test or units a professional engineer or architect stamp is only required on the structural load test or
calculations required by WAC calculations required by WAC 296-150V-0930296-150V-0930. We will retain the set with the original wet . We will retain the set with the original wet
stamp; andstamp; and
(d) A one-time initial filing fee, the design plan fee when required by WAC (d) A one-time initial filing fee, the design plan fee when required by WAC 296-150V-296-150V-
03000300, and the fee for each insignia (see WAC , and the fee for each insignia (see WAC 296-150V-3000296-150V-3000).).
(2) If you are requesting insignia under an approved design plan, your completed (2) If you are requesting insignia under an approved design plan, your completed
application must include:application must include:
(a) A completed insignia application form; and(a) A completed insignia application form; and
(b) The fee for each conversion vendor unit or medical unit insignia (see WAC (b) The fee for each conversion vendor unit or medical unit insignia (see WAC 296-296-
150V-3000150V-3000).).
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0230, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0230, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0230, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0230, filed 8/31/99, effective 10/1/99.]
296-150V-0240296-150V-0240
What documentation do you need to perform an alteration inspection?What documentation do you need to perform an alteration inspection?
If you alter a conversion vendor unit or medical unit, we must inspect the alteration.If you alter a conversion vendor unit or medical unit, we must inspect the alteration.
(1) Before we perform an alteration inspection and attach an alteration insignia, you (1) Before we perform an alteration inspection and attach an alteration insignia, you
must send us:must send us:
(a) Description of the proposed alteration;(a) Description of the proposed alteration;
(b) The plan review fee;(b) The plan review fee;
(c) The inspection fee; and(c) The inspection fee; and
(d) The insignia application and fee.(d) The insignia application and fee.
(2) A design plan review is not required if the alteration can be made without altering (2) A design plan review is not required if the alteration can be made without altering
any of the existing structure and if the alteration does not involve one or more of the systems any of the existing structure and if the alteration does not involve one or more of the systems
listed in WAC listed in WAC 296-150V-0300296-150V-0300..
Note
:
Note
:
A
ll fees are listed in WAC
A
ll fees are listed in WAC 296-150V-3000296-150V-3000 at the end of this chapter.at the end of this chapter.
Page 11 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0240, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0240, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0240, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0240, filed 8/31/99, effective 10/1/99.]
296-150V-0250296-150V-0250
How do I replace lost or damaged insignia?How do I replace lost or damaged insignia?
(1) If an insignia is lost or damaged after it is placed on a conversion vendor unit or (1) If an insignia is lost or damaged after it is placed on a conversion vendor unit or
medical unit, you may obtain a replacement insignia by contacting us and providing the medical unit, you may obtain a replacement insignia by contacting us and providing the
following:following:
(a) Your name, address, and telephone number;(a) Your name, address, and telephone number;
(b) The name of the manufacturer or person converting the conversion vendor unit or (b) The name of the manufacturer or person converting the conversion vendor unit or
medical unit;medical unit;
(c) The serial number;(c) The serial number;
(d) The manufacturer number (V#) if available;(d) The manufacturer number (V#) if available;
(e) The insignia number if available;(e) The insignia number if available;
(f) The required fee from WAC (f) The required fee from WAC 296-150V-3000296-150V-3000; and; and
(2) If we can determine that your unit previously had an insignia, we will:(2) If we can determine that your unit previously had an insignia, we will:
(a) Perform an inspection to ensure that no unauthorized remodeling has occurred; (a) Perform an inspection to ensure that no unauthorized remodeling has occurred;
andand
(b) Attach an insignia to your unit once we receive your insignia fee listed in WAC (b) Attach an insignia to your unit once we receive your insignia fee listed in WAC 296-296-
150V-3000150V-3000..
Note
:
Note
:
If unauthorized remodeling has occurred see WAC If unauthorized remodeling has occurred see WAC 296-150V-0200296-150V-0200 ..
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0250, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0250, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0300296-150V-0300
When is design-plan approval required?When is design-plan approval required?
Design plans for conversion vendor units and medical units are required for units that Design plans for conversion vendor units and medical units are required for units that
are sold, leased, or used in Washington state and must be approved when:are sold, leased, or used in Washington state and must be approved when:
(1) Conversion vendor units that contain one or more of the following components:(1) Conversion vendor units that contain one or more of the following components:
(a) Concentrated loads exceeding five hundred pounds (see WAC (a) Concentrated loads exceeding five hundred pounds (see WAC 296-150V-0930296-150V-0930););
(b) Fuel gas piping systems and equipment;(b) Fuel gas piping systems and equipment;
(c) Solid fuel burning equipment;(c) Solid fuel burning equipment;
(d) Fire suppression systems;(d) Fire suppression systems;
(e) Commercial hoods;(e) Commercial hoods;
(f) Electrical systems and equipment in excess of 30 amps/120 volts;(f) Electrical systems and equipment in excess of 30 amps/120 volts;
(g) Electrical systems with more than five circuits;(g) Electrical systems with more than five circuits;
(h) Electrical systems incorporating photovoltaic energy, fuel cell energy, or other (h) Electrical systems incorporating photovoltaic energy, fuel cell energy, or other
alternative energy systems;alternative energy systems;
(i) Plumbing drainage systems conveying solid or bodily waste.(i) Plumbing drainage systems conveying solid or bodily waste.
(2) Medical units.(2) Medical units.
(3) Modification of an approved design plan through addendums;(3) Modification of an approved design plan through addendums;
Page 1
2
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(4) Addition of options to an approved design plan through addendums.(4) Addition of options to an approved design plan through addendums.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0300, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0300, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0300, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0300, filed 8/31/99, effective 10/1/99.]
296-150V-0310296-150V-0310
Who can approve design plans?Who can approve design plans?
Your design plan must be approved by the department.Your design plan must be approved by the department.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0310, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0310, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0320296-150V-0320
What must I provide with my request for conversion vendor unit or medical What must I provide with my request for conversion vendor unit or medical
unit design-plan approval by the department?unit design-plan approval by the department?
(1) All requests for design-plan approval must include:(1) All requests for design-plan approval must include:
(a) A completed design-plan approval request form;(a) A completed design-plan approval request form;
(b) Two sets of design plans, specifications and test results and procedures necessary (b) Two sets of design plans, specifications and test results and procedures necessary
for a complete evaluation of the design;for a complete evaluation of the design;
(c) Receipt of the design-plan fee listed in WAC (c) Receipt of the design-plan fee listed in WAC 296-150V-3000296-150V-3000;;
(d) Receipt of the initial design-plan filing fee and the initial design-plan fee.(d) Receipt of the initial design-plan filing fee and the initial design-plan fee.
(2) If a structural analysis or test is required for a concentrated floor load, at least one (2) If a structural analysis or test is required for a concentrated floor load, at least one
set of design plans must have an original wet stamp from a professional engineer or architect set of design plans must have an original wet stamp from a professional engineer or architect
licensed in Washington state. All new, renewed, and resubmitted plans, specifications, reports licensed in Washington state. All new, renewed, and resubmitted plans, specifications, reports
and structural calculations prepared by or prepared under the engineer or architect's direct and structural calculations prepared by or prepared under the engineer or architect's direct
supervision shall be signed, dated and stamped with his or her seal. Specifications, reports, supervision shall be signed, dated and stamped with his or her seal. Specifications, reports,
and structural calculations may be stamped only on the first sheet, provided this first sheet and structural calculations may be stamped only on the first sheet, provided this first sheet
identifies all of the sheets that follow are included and identified in the same manner. Plans identifies all of the sheets that follow are included and identified in the same manner. Plans
that have not been prepared by or under the engineer's or architect's supervision shall be that have not been prepared by or under the engineer's or architect's supervision shall be
reviewed and he or she must prepare a report concerning the plans. This report must:reviewed and he or she must prepare a report concerning the plans. This report must:
(a) Identify which drawings have been reviewed by drawing number and date;(a) Identify which drawings have been reviewed by drawing number and date;
(b) Include a statement that the plans are in compliance with current Washington state (b) Include a statement that the plans are in compliance with current Washington state
regulations; andregulations; and
(c) Be stamped and signed by the reviewer.(c) Be stamped and signed by the reviewer.
(3) Any deficiencies shall be corrected on the drawings before submitting to the (3) Any deficiencies shall be corrected on the drawings before submitting to the
department or be included in the report and identify as to how they are to be corrected. This department or be included in the report and identify as to how they are to be corrected. This
report shall be attached to the plan(s) that were reviewed. We will retain the set with the report shall be attached to the plan(s) that were reviewed. We will retain the set with the
original wet stamp.original wet stamp.
(4) Electrical plan review for educational, institutional or health care facilities and other (4) Electrical plan review for educational, institutional or health care facilities and other
buildings. Plan review is a part of the electrical inspection process; its primary purpose is to buildings. Plan review is a part of the electrical inspection process; its primary purpose is to
determine:determine:
Page 1
3
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(a) That loads and service/feeder conductors are calculated and sized according to the (a) That loads and service/feeder conductors are calculated and sized according to the
proper NCE or WAC article or section;proper NCE or WAC article or section;
(b) The classification of hazardous locations; and(b) The classification of hazardous locations; and
(c) The proper design of emergency and standby systems.(c) The proper design of emergency and standby systems.
(5) All electrical plans for new or altered electrical installations in educational, (5) All electrical plans for new or altered electrical installations in educational,
institutional, and health or personal care occupancies classified or defined in this chapter must institutional, and health or personal care occupancies classified or defined in this chapter must
be reviewed and approved before the electrical installation or alteration is started. Approved be reviewed and approved before the electrical installation or alteration is started. Approved
plans must be available for use during the electrical installation or alteration and for use by the plans must be available for use during the electrical installation or alteration and for use by the
electrical inspector.electrical inspector.
(6) All electrical plans for educational facilities, hospitals and nursing homes must be (6) All electrical plans for educational facilities, hospitals and nursing homes must be
prepared by, or under the direction of, a consulting engineer registered under chapter prepared by, or under the direction of, a consulting engineer registered under chapter 18.4318.43
RCW in compliance with chapters RCW in compliance with chapters 246-320246-320, 180-29, and , 180-29, and 388-97388-97 WAC as applicable, and WAC as applicable, and
stamped with the engineer's mark and signature.stamped with the engineer's mark and signature.
(7) Plans to be reviewed by the department must be legible, identify the name and (7) Plans to be reviewed by the department must be legible, identify the name and
classification of the facility, clearly indicate the scope and nature of the installation and the classification of the facility, clearly indicate the scope and nature of the installation and the
person or firm responsible for the electrical plans. The plans must clearly show the electrical person or firm responsible for the electrical plans. The plans must clearly show the electrical
installation or alteration in floor plan view, include switchboard and/or panel board schedules installation or alteration in floor plan view, include switchboard and/or panel board schedules
and when a service or feeder is to be installed or altered, must include a riser diagram, load and when a service or feeder is to be installed or altered, must include a riser diagram, load
calculation, fault current calculation and interrupting rating of equipment. Where existing calculation, fault current calculation and interrupting rating of equipment. Where existing
electrical systems are to supply additional loads, the plans must include documentation that electrical systems are to supply additional loads, the plans must include documentation that
proves adequate capacity and ratings. The plans must be submitted with a plan review proves adequate capacity and ratings. The plans must be submitted with a plan review
submittal form available from the department.submittal form available from the department.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 05-23-002, § 296-150V-0320, filed 11/3/05, RCW. WSR 05-23-002, § 296-150V-0320, filed 11/3/05,
effective 12/4/05; WSR 99-18-069, § 296-150V-0320, filed 8/31/99, effective 10/1/99.]effective 12/4/05; WSR 99-18-069, § 296-150V-0320, filed 8/31/99, effective 10/1/99.]
296-150V-0340296-150V-0340
When is an engineering analysis or structural load test for design plans When is an engineering analysis or structural load test for design plans
required?required?
An engineering analysis or structural load test may be required when there are An engineering analysis or structural load test may be required when there are
concentrated loads of 500 pounds or more in a 16 square feet or less area.concentrated loads of 500 pounds or more in a 16 square feet or less area.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0340, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0340, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0350296-150V-0350
What must test procedures and results for design plans include?What must test procedures and results for design plans include?
(1) Test to a design must be witnessed by a professional engineer or architect licensed (1) Test to a design must be witnessed by a professional engineer or architect licensed
in Washington or by a department employee.in Washington or by a department employee.
(2) Test reports must contain the following items:(2) Test reports must contain the following items:
(a) A description of the methods or standards that applied to the test;(a) A description of the methods or standards that applied to the test;
(b) Drawings and a description of the item tested;(b) Drawings and a description of the item tested;
Page 1
4
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(c) A description of the test set-up;(c) A description of the test set-up;
(d) The procedure used to verify the correct load;(d) The procedure used to verify the correct load;
(e) The procedure used to measure each condition;(e) The procedure used to measure each condition;
(f) Test data, including applicable graphs and observations of the characteristics and (f) Test data, including applicable graphs and observations of the characteristics and
behavior of the item tested; andbehavior of the item tested; and
(g) Analysis, comments, and conclusion.(g) Analysis, comments, and conclusion.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0350, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0350, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0380296-150V-0380
What happens if you approve my design plan?What happens if you approve my design plan?
(1) Your design plan will be approved if it meets the requirements of this chapter.(1) Your design plan will be approved if it meets the requirements of this chapter.
(2) We will send you an approved copy of the design plan with the design-plan (2) We will send you an approved copy of the design plan with the design-plan
approval number.approval number.
(3) You must keep copies of the approved design plan available for inspection at each (3) You must keep copies of the approved design plan available for inspection at each
location where the conversion vendor unit or medical unit is built.location where the conversion vendor unit or medical unit is built.
(4) If your design plan is not approved, you will be notified in writing of plan (4) If your design plan is not approved, you will be notified in writing of plan
deficiencies. You may send a corrected design plan to us along with the resubmittal fee listed deficiencies. You may send a corrected design plan to us along with the resubmittal fee listed
in WAC in WAC 296-150V-3000296-150V-3000..
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0380, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0380, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0390296-150V-0390
If my design plan is not approved, how much time do I have to submit a If my design plan is not approved, how much time do I have to submit a
corrected design plan?corrected design plan?
(1) You have ninety days to correct and resubmit your original design plan and send us (1) You have ninety days to correct and resubmit your original design plan and send us
the resubmittal fee after we notify you of plan deficiencies. After ninety days, your initial design the resubmittal fee after we notify you of plan deficiencies. After ninety days, your initial design
plan is returned to you.plan is returned to you.
(2) If you submit your corrected design plan after ninety days, the initial design-plan (2) If you submit your corrected design plan after ninety days, the initial design-plan
fee is required instead of the resubmittal fee. (See WAC fee is required instead of the resubmittal fee. (See WAC 296-150V-3000296-150V-3000.).)
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0390, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0390, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0400296-150V-0400
What happens after my design plan is approved?What happens after my design plan is approved?
Page 1
5
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
Once your design plan is approved, we will inspect each conversion vendor unit and Once your design plan is approved, we will inspect each conversion vendor unit and
medical unit.medical unit.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0400, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0400, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0410296-150V-0410
When does my design plan expire?When does my design plan expire?
(1) Your conversion vendor unit or medical unit one-year design plan expires either (1) Your conversion vendor unit or medical unit one-year design plan expires either
one year after approval or when there is an electrical code change. You must submit new one year after approval or when there is an electrical code change. You must submit new
design plans for approval when there is a state building code cycle change. You may use your design plans for approval when there is a state building code cycle change. You may use your
design plans to order insignia as long as they comply with the applicable codes.design plans to order insignia as long as they comply with the applicable codes.
(2) All National Electrical Code (NEC) amendments may be incorporated by an (2) All National Electrical Code (NEC) amendments may be incorporated by an
addendum to your design plan.addendum to your design plan.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0410, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0410, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0415296-150V-0415
Who approves addendums to design plans?Who approves addendums to design plans?
Any addendums to a design plan must be approved by the department.Any addendums to a design plan must be approved by the department.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0415, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0415, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0495296-150V-0495
Contractor deposit accounts.Contractor deposit accounts.
Manufacturers are required to open and maintain, for the purpose of inspection Manufacturers are required to open and maintain, for the purpose of inspection
payments, a deposit account. Funds, for the purpose of inspections performed by the payments, a deposit account. Funds, for the purpose of inspections performed by the
department, must be withdrawn from the account and all inspections paid in full prior to an department, must be withdrawn from the account and all inspections paid in full prior to an
insignia being placed on the manufactured unit.insignia being placed on the manufactured unit.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 12-15-061, § 296-150V-0495, filed 7/17/12, RCW. WSR 12-15-061, § 296-150V-0495, filed 7/17/12,
effective 9/1/12.]effective 9/1/12.]
Page 1
6
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0500296-150V-0500
When is an inspection required?When is an inspection required?
(1) Before we issue an insignia, each unit manufactured or converted must be (1) Before we issue an insignia, each unit manufactured or converted must be
inspected as many times as required to show compliance with this chapter.inspected as many times as required to show compliance with this chapter.
(2) Before we issue an insignia, a conversion vendor unit or medical unit must be (2) Before we issue an insignia, a conversion vendor unit or medical unit must be
inspected at the manufacturing location as many times as required. Inspections may include, inspected at the manufacturing location as many times as required. Inspections may include,
but are not limited to:but are not limited to:
(a) A "cover" inspection during construction of the unit before the electrical, plumbing, (a) A "cover" inspection during construction of the unit before the electrical, plumbing,
mechanical, and structural systems (if required) are covered;mechanical, and structural systems (if required) are covered;
(b) Insulation and vapor barrier inspection, if required; and(b) Insulation and vapor barrier inspection, if required; and
(c) A final inspection after the conversion vendor unit or medical unit is complete.(c) A final inspection after the conversion vendor unit or medical unit is complete.
(3) If we discover a violation during inspection, we will issue a notice of (3) If we discover a violation during inspection, we will issue a notice of
noncompliance. You can correct the violation during the inspection. If you cannot correct the noncompliance. You can correct the violation during the inspection. If you cannot correct the
violation during inspection, you must leave the item uncovered until we approve your violation during inspection, you must leave the item uncovered until we approve your
correction.correction.
(4) If a conversion vendor unit or medical unit is damaged in transit to the building site (4) If a conversion vendor unit or medical unit is damaged in transit to the building site
or during on-site installation, it must be inspected. This is considered an alteration inspection. or during on-site installation, it must be inspected. This is considered an alteration inspection.
(See WAC (See WAC 296-150V-0240296-150V-0240.).)
(5) Approved plans must be available.(5) Approved plans must be available.
(6) Once your unit is inspected and approved we will attach the insignia. Before we (6) Once your unit is inspected and approved we will attach the insignia. Before we
issue an insignia, each conversion vendor unit or medical unit is inspected as follows:issue an insignia, each conversion vendor unit or medical unit is inspected as follows:
(a) Inspection(s) during conversion or alteration of a conversion vendor unit or medical (a) Inspection(s) during conversion or alteration of a conversion vendor unit or medical
unit; andunit; and
(b) A final inspection after the conversion vendor unit or medical unit is complete.(b) A final inspection after the conversion vendor unit or medical unit is complete.
Note
:
Note
:
Each conversion vendor unit or medical unit must have a serial number so we can track inspections
.
Each conversion vendor unit or medical unit must have a serial number so we can track inspections
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0500, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0500, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0510296-150V-0510
How do I request an inspection?How do I request an inspection?
You must contact us and we will let you know where your request for inspection should You must contact us and we will let you know where your request for inspection should
be submitted. Our address is noted in the definition of department in WAC be submitted. Our address is noted in the definition of department in WAC 296-150V-0020296-150V-0020..
(1) We must receive in-state inspection requests at least seven calendar days prior to (1) We must receive in-state inspection requests at least seven calendar days prior to
the date that you want the inspection.the date that you want the inspection.
(2) We must receive out-of-state inspection requests at least fourteen calendar days (2) We must receive out-of-state inspection requests at least fourteen calendar days
prior to the date that you want the inspection.prior to the date that you want the inspection.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0510, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0510, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 1
7
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0520296-150V-0520
What happens if my conversion vendor unit or medical unit passes What happens if my conversion vendor unit or medical unit passes
inspection?inspection?
If your conversion vendor unit or medical unit passes inspection and you have met the If your conversion vendor unit or medical unit passes inspection and you have met the
other requirements of this chapter, we will attach the insignia.other requirements of this chapter, we will attach the insignia.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0520, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0520, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0530296-150V-0530
Am I charged if I request an inspection but I am not prepared?Am I charged if I request an inspection but I am not prepared?
(1) If you ask us to inspect a conversion vendor unit or medical unit within Washington (1) If you ask us to inspect a conversion vendor unit or medical unit within Washington
state but you are not prepared when we arrive, you must pay the inspection fee and travel state but you are not prepared when we arrive, you must pay the inspection fee and travel
(see WAC (see WAC 296-150V-3000296-150V-3000).).
(2) If the inspection is outside of Washington state and you are not prepared, you must (2) If the inspection is outside of Washington state and you are not prepared, you must
pay the inspection fee, travel, and per diem expenses (see WAC pay the inspection fee, travel, and per diem expenses (see WAC 296-150V-3000296-150V-3000).).
[Statutory Authority: RCW [Statutory Authority: RCW 43.22.34043.22.340, , 43.22.35043.22.350, , 43.22.35543.22.355, , 43.22.36043.22.360, , 43.22.40043.22.400, , 43.22.43243.22.432, ,
43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.45043.22.450, , 43.22.48043.22.480, and , and 43.22.48543.22.485. WSR 00-17-148, § 296-150V-. WSR 00-17-148, § 296-150V-
0530, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter 0530, filed 8/22/00, effective 9/30/00. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-RCW. WSR 99-18-
069, § 296-150V-0530, filed 8/31/99, effective 10/1/99.]069, § 296-150V-0530, filed 8/31/99, effective 10/1/99.]
296-150V-0540296-150V-0540
Who inspects a conversion vendor unit or medical unit installation at the Who inspects a conversion vendor unit or medical unit installation at the
building site or event location?building site or event location?
The local enforcement agency (city or county) must approve the installation. The local enforcement agency (city or county) must approve the installation.
Alterations to conversion vendor units or medical units must be inspected and approved by us.Alterations to conversion vendor units or medical units must be inspected and approved by us.
Note
:
Note
:
The local enforcement agency may not open the concealed construction of a conversion vendor unit or medical unit The local enforcement agency may not open the concealed construction of a conversion vendor unit or medical unit
to inspect it if our insignia is attached
.
to inspect it if our insignia is attached
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0540, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0540, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0550296-150V-0550
Do you allow a conversion vendor unit or medical unit to be completed at Do you allow a conversion vendor unit or medical unit to be completed at
the installation site?the installation site?
No. Conversion vendor units or medical units must be completed at the manufacturing No. Conversion vendor units or medical units must be completed at the manufacturing
location before an insignia is attached.location before an insignia is attached.
Page 18 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0550, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0550, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0560296-150V-0560
What happens if I receive a notice of noncompliance after inspection of the What happens if I receive a notice of noncompliance after inspection of the
alteration to my conversion vendor unit or medical unit?alteration to my conversion vendor unit or medical unit?
(1) If your conversion vendor unit or medical unit alteration does not pass our (1) If your conversion vendor unit or medical unit alteration does not pass our
inspection, you will receive a notice of noncompliance. The notice of noncompliance explains inspection, you will receive a notice of noncompliance. The notice of noncompliance explains
what items must be corrected.what items must be corrected.
(2) You have twenty days after receiving the notice of noncompliance to send us a (2) You have twenty days after receiving the notice of noncompliance to send us a
written response to explain how you will correct the violations.written response to explain how you will correct the violations.
(3) You are not allowed to sell, lease, offer for sale or use the altered conversion (3) You are not allowed to sell, lease, offer for sale or use the altered conversion
vendor unit or medical unit until you correct the violations. We must inspect and approve the vendor unit or medical unit until you correct the violations. We must inspect and approve the
corrections, and you must pay any required inspection and insignia fees listed in WAC corrections, and you must pay any required inspection and insignia fees listed in WAC 296-296-
150V-3000150V-3000..
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0560, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0560, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0580296-150V-0580
Must I obtain an insignia for used conversion vendor units or medical Must I obtain an insignia for used conversion vendor units or medical
units?units?
All used conversion vendor units or medical units that are to be installed on a building All used conversion vendor units or medical units that are to be installed on a building
site or used in Washington state must have an insignia of approval from us.site or used in Washington state must have an insignia of approval from us.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 16-13-119, § 296-150V-0580, filed 6/21/16, RCW. WSR 16-13-119, § 296-150V-0580, filed 6/21/16,
effective 6/21/16; WSR 99-18-069, § 296-150V-0580, filed 8/31/99, effective 10/1/99.]effective 6/21/16; WSR 99-18-069, § 296-150V-0580, filed 8/31/99, effective 10/1/99.]
296-150V-0590296-150V-0590
How do I obtain insignia for used conversion vendor units or medical How do I obtain insignia for used conversion vendor units or medical
units?units?
We consider used conversion vendor units and medical units as new units for We consider used conversion vendor units and medical units as new units for
purposes of insignia approval. To obtain insignia, you must:purposes of insignia approval. To obtain insignia, you must:
(1) Have the design plan approved (see WAC (1) Have the design plan approved (see WAC 296-150V-0300296-150V-0300 and and 296-150V-0320296-150V-0320););
(2) Purchase insignia (see WAC (2) Purchase insignia (see WAC 296-150V-0200296-150V-0200 through through 296-150V-0230296-150V-0230); and); and
(3) Pass a unit inspection (see WAC (3) Pass a unit inspection (see WAC 296-150V-0500296-150V-0500 through through 296-150V-0560296-150V-0560).).
Note
:
Note
:
Y
ou will be required to open up as much of the construction of the unit as is necessary for inspection to show
Y
ou will be required to open up as much of the construction of the unit as is necessary for inspection to show
compliance with your approved design plan
.
compliance with your approved design plan
.
Page 1
9
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0590, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0590, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0700296-150V-0700
Must manufacturers of conversion vendor units and medical units notify Must manufacturers of conversion vendor units and medical units notify
you if they manufacture at more than one location?you if they manufacture at more than one location?
(1) If you are manufacturing conversion vendor units and medical units at more than (1) If you are manufacturing conversion vendor units and medical units at more than
one location, approved design plans must be available at each manufacturing location.one location, approved design plans must be available at each manufacturing location.
(2) You must send us the following information for each manufacturing location:(2) You must send us the following information for each manufacturing location:
(a) Company name;(a) Company name;
(b) Mailing and physical address; and(b) Mailing and physical address; and
(c) Phone and fax number, if available.(c) Phone and fax number, if available.
(3) You must update this information as it changes.(3) You must update this information as it changes.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0700, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0700, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0710296-150V-0710
Must manufacturers of conversion vendor units and medical units notify Must manufacturers of conversion vendor units and medical units notify
you of a change in business name or address?you of a change in business name or address?
If you are moving you must notify us in writing prior to a change of business name or If you are moving you must notify us in writing prior to a change of business name or
address and include the change of name and address.address and include the change of name and address.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0710, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0710, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0720296-150V-0720
Must manufacturers of conversion vendor units and medical units notify Must manufacturers of conversion vendor units and medical units notify
you of a change in business ownership?you of a change in business ownership?
(1) When a manufacturer changes ownership, the new owner must notify us in writing (1) When a manufacturer changes ownership, the new owner must notify us in writing
immediately.immediately.
(2) A new owner may continue to manufacture the units according to a prior approved (2) A new owner may continue to manufacture the units according to a prior approved
design plan if the prior owner provides written releases of the design plan.design plan if the prior owner provides written releases of the design plan.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0720, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0720, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 20 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-0800296-150V-0800
What codes apply to conversion vendor units or medical units?What codes apply to conversion vendor units or medical units?
(1) A conversion vendor unit or medical unit must comply with the following codes (1) A conversion vendor unit or medical unit must comply with the following codes
where applicable:where applicable:
(a) The current edition of the International Mechanical Code, with the amendments (a) The current edition of the International Mechanical Code, with the amendments
made by the Washington State Building Code Council, chapter made by the Washington State Building Code Council, chapter 51-5251-52 WAC.WAC.
(b)(i) For conversion vending/medical units Article 551, Parts I through VI of National (b)(i) For conversion vending/medical units Article 551, Parts I through VI of National
Electrical Code/National Fire Protection Agency (NFPA) 70, current edition or Article 552, Electrical Code/National Fire Protection Agency (NFPA) 70, current edition or Article 552,
Parts I through V Article of National Electrical Code/National Fire Protection Agency (NFPA) Parts I through V Article of National Electrical Code/National Fire Protection Agency (NFPA)
70, current edition.70, current edition.
(ii) For medical units the National Electrical Code (NFPA 70, current edition) as (ii) For medical units the National Electrical Code (NFPA 70, current edition) as
referenced in Article 517 for Patient Care Areas and chapter referenced in Article 517 for Patient Care Areas and chapter 296-46B296-46B WAC.WAC.
(c) Chapter 7 of the National Fire Protection Association (NFPA 1192), current edition (c) Chapter 7 of the National Fire Protection Association (NFPA 1192), current edition
or the Uniform Plumbing Code as adopted and amended according to chapter or the Uniform Plumbing Code as adopted and amended according to chapter 19.2719.27 RCW.RCW.
(d) The Washington State Building Code Council, chapter (d) The Washington State Building Code Council, chapter 51-5051-50 WAC, International WAC, International
Building Code, Chapter 11, Accessibility as applies to the exterior of the unit relating to Building Code, Chapter 11, Accessibility as applies to the exterior of the unit relating to
customer service facilities in section 1105.4.7.customer service facilities in section 1105.4.7.
(2) Provide minimum health and safety to the occupants of conversion vendor units (2) Provide minimum health and safety to the occupants of conversion vendor units
and medical units and the public, and demonstrate journeyman quality of work of the various and medical units and the public, and demonstrate journeyman quality of work of the various
trades.trades.
(3) Requirements for any size, weight, or quality of material modified by the terms (3) Requirements for any size, weight, or quality of material modified by the terms
"minimum," "not less than," "at least," and similar expressions are minimum standards. The "minimum," "not less than," "at least," and similar expressions are minimum standards. The
conversion vendor unit or medical unit may exceed these rules provided the deviation does conversion vendor unit or medical unit may exceed these rules provided the deviation does
not result in inferior installation or defeat the purpose and intent of this chapter.not result in inferior installation or defeat the purpose and intent of this chapter.
Exception
:
Exception
:
Sign circuits required by Article 600 of the National Electrical Code will not be required.Sign circuits required by Article 600 of the National Electrical Code will not be required.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 12-15-061, § 296-150V-0800, filed 7/17/12, RCW. WSR 12-15-061, § 296-150V-0800, filed 7/17/12,
effective 9/1/12. Statutory Authority: RCW effective 9/1/12. Statutory Authority: RCW 43.22.34043.22.340, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, ,
43.22.43443.22.434, , 43.22.48043.22.480, and , and 43.22.48543.22.485, 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RCW. WSR 03-12-044, RCW. WSR 03-12-044,
§ 296-150V-0800, filed 5/30/03, effective 6/30/03. Statutory Authority: RCW § 296-150V-0800, filed 5/30/03, effective 6/30/03. Statutory Authority: RCW 43.22.35043.22.350, ,
43.22.43443.22.434, , 43.22.48043.22.480, , 43.22.50043.22.500, , 18.27.04018.27.040, , 18.27.07018.27.070, , 18.27.07518.27.075, , 70.87.03070.87.030, , 19.28.04119.28.041, ,
19.28.05119.28.051, , 19.28.10119.28.101, , 19.28.12119.28.121, , 19.28.16119.28.161, , 19.28.20119.28.201, , 19.28.21119.28.211, , 19.28.34119.28.341, 2001 c 7, 2002 , 2001 c 7, 2002
c 249, and chapters c 249, and chapters 19.2819.28, 43.22, 18.27, and , 43.22, 18.27, and 70.8770.87 RCW. WSR 02-12-022, § 296-150V-0800, RCW. WSR 02-12-022, § 296-150V-0800,
filed 5/28/02, effective 6/28/02. Statutory Authority: Chapter filed 5/28/02, effective 6/28/02. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § RCW. WSR 99-18-069, §
296-150V-0800, filed 8/31/99, effective 10/1/99.]296-150V-0800, filed 8/31/99, effective 10/1/99.]
296-150V-0930296-150V-0930
When are structural load tests or structural calculations required?When are structural load tests or structural calculations required?
(1) A structural analysis is required when a unit has a concentrated floor load of 500 (1) A structural analysis is required when a unit has a concentrated floor load of 500
pounds or more in a 16 square feet or less area.pounds or more in a 16 square feet or less area.
(2) The structural load test can be used as an alternative.(2) The structural load test can be used as an alternative.
(a) A structural assembly tested for qualification must sustain the design dead load (a) A structural assembly tested for qualification must sustain the design dead load
plus the superimposed design live loads for vendor units and medical units assembly.plus the superimposed design live loads for vendor units and medical units assembly.
Page 21 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(b) An assembly failure is defined as a rupture, fracture, or residual deflection which is (b) An assembly failure is defined as a rupture, fracture, or residual deflection which is
greater than the limits.greater than the limits.
Note
:
Note
:
We will provide test procedure forms upon request.We will provide test procedure forms upon request.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0930, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0930, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-0950296-150V-0950
What requirements apply to roof coverings?What requirements apply to roof coverings?
(1) The roof covering must be securely fastened in an approved manner to the (1) The roof covering must be securely fastened in an approved manner to the
supporting roof construction and must provide weather protection for the vendor unit and the supporting roof construction and must provide weather protection for the vendor unit and the
occupants.occupants.
(2) Exterior covering materials, including metal coverings, must be moisture and (2) Exterior covering materials, including metal coverings, must be moisture and
weather resistant and contain corrosion resistant fasteners to prevent wind and rain weather resistant and contain corrosion resistant fasteners to prevent wind and rain
deterioration.deterioration.
Note
:
Note
:
Electro-plated, electro-deposited zinc, and electro-galvanized staples are not considered corrosion-resistant Electro-plated, electro-deposited zinc, and electro-galvanized staples are not considered corrosion-resistant
materials
.
materials
.
(3) All exterior openings or penetrations into the conversion vendor unit or medical unit (3) All exterior openings or penetrations into the conversion vendor unit or medical unit
around piping, ducts, plenums, or vents must be sealed with moisture-resistant material.around piping, ducts, plenums, or vents must be sealed with moisture-resistant material.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-0950, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-0950, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1040296-150V-1040
Are there floor requirements?Are there floor requirements?
Wood floors must be made moisture resistant by an overlay of nonabsorbent material Wood floors must be made moisture resistant by an overlay of nonabsorbent material
applied with water-resistant adhesive.applied with water-resistant adhesive.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1040, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1040, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1070296-150V-1070
What requirements apply to floor closure material?What requirements apply to floor closure material?
(1) Floor closure material around piping, ducts, plenums, or vents must prevent (1) Floor closure material around piping, ducts, plenums, or vents must prevent
damage to the underside of the vendor unit due to air, water, insects, dust, and be rodent damage to the underside of the vendor unit due to air, water, insects, dust, and be rodent
resistant.resistant.
(2) The floor closure material must meet ASTM D-781 standard or equal and be (2) The floor closure material must meet ASTM D-781 standard or equal and be
installed as follows:installed as follows:
(a) Fibrous material (with or without patches) must meet or exceed the level of 48 inch-(a) Fibrous material (with or without patches) must meet or exceed the level of 48 inch-
pounds of puncture resistance as tested.pounds of puncture resistance as tested.
Page 2
2
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(b) Patching material must be installed according to installation instructions furnished (b) Patching material must be installed according to installation instructions furnished
by the supplier of the material.by the supplier of the material.
(c) The material must be suitable for patches and the patch life must be equivalent to (c) The material must be suitable for patches and the patch life must be equivalent to
the material life.the material life.
Note
:
Note
:
A
STM D-781 is a puncture test for bottom board materials
.A
STM D-781 is a puncture test for bottom board materials
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1070, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1070, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1090296-150V-1090
What are the standards for equipment and installations?What are the standards for equipment and installations?
The manufacturer's equipment and installation specifications must be followed. Other The manufacturer's equipment and installation specifications must be followed. Other
approved standards are acceptable when:approved standards are acceptable when:
• Installed according to the manufacturer's installation instructions; and• Installed according to the manufacturer's installation instructions; and
• Approved by a listing or testing agency.• Approved by a listing or testing agency.
Note
:
Note
:
Gas furnaces, gas water heaters, and gas refrigerators must be sealed combustion or completely separated from theGas furnaces, gas water heaters, and gas refrigerators must be sealed combustion or completely separated from the
interior of the conversion vendor unit or medical unit
.
interior of the conversion vendor unit or medical unit
.
[Statutory Authority: RCW [Statutory Authority: RCW 43.22.34043.22.340, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.48043.22.480, ,
and and 43.22.48543.22.485, 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RCW. WSR 03-12-044, § 296-150V-1090, filed RCW. WSR 03-12-044, § 296-150V-1090, filed
5/30/03, effective 6/30/03. Statutory Authority: Chapter 5/30/03, effective 6/30/03. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-RCW. WSR 99-18-069, § 296-
150V-1090, filed 8/31/99, effective 10/1/99.]150V-1090, filed 8/31/99, effective 10/1/99.]
296-150V-1100296-150V-1100
What are the flame-spread limitations?What are the flame-spread limitations?
The flame-spread requirements are that all walls and ceilings must be of 200 flame-The flame-spread requirements are that all walls and ceilings must be of 200 flame-
spread or less.spread or less.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1100, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1100, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1110296-150V-1110
Combustible limitations.Combustible limitations.
(1) The exposed wall adjacent to the cooking range must be 50 flame-spread or less, (1) The exposed wall adjacent to the cooking range must be 50 flame-spread or less,
such as 5/16 inch gypsum board or material having equivalent fire protective properties.such as 5/16 inch gypsum board or material having equivalent fire protective properties.
(2) All openings for pipes and vents in furnace and water heater spaces shall be tight-(2) All openings for pipes and vents in furnace and water heater spaces shall be tight-
fitted or fire-stopped.fitted or fire-stopped.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1110, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1110, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 2
3
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-1120296-150V-1120
What are the standards for wall and cabinet protection?What are the standards for wall and cabinet protection?
The bottom and sides of combustible cabinets over cooking appliances or tops The bottom and sides of combustible cabinets over cooking appliances or tops
including a space of 6 inches from the edge of the burners must be protected with at least including a space of 6 inches from the edge of the burners must be protected with at least
5/16 inch sheetrock with a 25 flame-spread. This material must be behind deep-fat fryers, 5/16 inch sheetrock with a 25 flame-spread. This material must be behind deep-fat fryers,
grills, ranges, and other cooking appliances. It must extend 6 inches beyond the edge of the grills, ranges, and other cooking appliances. It must extend 6 inches beyond the edge of the
appliance and range hood.appliance and range hood.
(1) Range hoods for commercial equipment must meet the requirements of the (1) Range hoods for commercial equipment must meet the requirements of the
mechanical code such as fire suppression, etc.mechanical code such as fire suppression, etc.
(2) Range hoods for noncommercial equipment may be of a residential type.(2) Range hoods for noncommercial equipment may be of a residential type.
(3) The hood must be centered over and at least as wide as the top of the cooking (3) The hood must be centered over and at least as wide as the top of the cooking
appliance.appliance.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1120, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1120, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1170296-150V-1170
What are the light and ventilation requirements?What are the light and ventilation requirements?
Each bathroom must be provided with artificial light and with a window having at least Each bathroom must be provided with artificial light and with a window having at least
1/2 square feet of glazed area that can be fully opened, except where a mechanical ventilation 1/2 square feet of glazed area that can be fully opened, except where a mechanical ventilation
system is installed. Any mechanical ventilation system must exhaust directly to the outside of system is installed. Any mechanical ventilation system must exhaust directly to the outside of
the conversion vendor unit or medical unit.the conversion vendor unit or medical unit.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1170, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1170, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1180296-150V-1180
What requirements apply to conversion vendor unit exits?What requirements apply to conversion vendor unit exits?
At least one conversion vending unit exit or medical unit exit must meet the following At least one conversion vending unit exit or medical unit exit must meet the following
requirements:requirements:
(1) Exterior doors must be constructed for exterior use.(1) Exterior doors must be constructed for exterior use.
(2) The exterior door must be at least a twenty-eight inch wide clear opening by (2) The exterior door must be at least a twenty-eight inch wide clear opening by
seventy-two inches high.seventy-two inches high.
(3) Locks must be operable from the interior of the unit without use of a key.(3) Locks must be operable from the interior of the unit without use of a key.
(4) Exit doors may either be hinged or sliding. Roll-up doors may not be used to meet (4) Exit doors may either be hinged or sliding. Roll-up doors may not be used to meet
the requirements of this section.the requirements of this section.
(5) Existing units with doors less than twenty-eight inches in width must have a second (5) Existing units with doors less than twenty-eight inches in width must have a second
means of exit. The second means of exit for converted units shall be twenty-four inches by means of exit. The second means of exit for converted units shall be twenty-four inches by
Page 2
4
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
seventeen inches, and for newly built units exits must be a minimum of five square feet of seventeen inches, and for newly built units exits must be a minimum of five square feet of
openable area.openable area.
(6) Pass-through windows shall be safety glazed based on the IBC Section 2406.1.(6) Pass-through windows shall be safety glazed based on the IBC Section 2406.1.
Exception
:
Exception
:
When there are employees, a minimum of twenty-eight inches clear opening must be provided
.
When there are employees, a minimum of twenty-eight inches clear opening must be provided
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 12-15-061, § 296-150V-1180, filed 7/17/12, RCW. WSR 12-15-061, § 296-150V-1180, filed 7/17/12,
effective 9/1/12. Statutory Authority: Chapter effective 9/1/12. Statutory Authority: Chapter 43.2243.22 RCW and 2003 c 291. WSR 05-01-102, § RCW and 2003 c 291. WSR 05-01-102, §
296-150V-1180, filed 12/14/04, effective 2/1/05. Statutory Authority: RCW 296-150V-1180, filed 12/14/04, effective 2/1/05. Statutory Authority: RCW 43.22.34043.22.340, ,
43.22.35043.22.350, , 43.22.35543.22.355, , 43.22.36043.22.360, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.45043.22.450, ,
43.22.48043.22.480, and , and 43.22.48543.22.485. WSR 00-17-148, § 296-150V-1180, filed 8/22/00, effective 9/30/00. . WSR 00-17-148, § 296-150V-1180, filed 8/22/00, effective 9/30/00.
Statutory Authority: Chapter Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1180, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1180, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1185296-150V-1185
What exit door requirements apply to self-propelled medical unit exits?What exit door requirements apply to self-propelled medical unit exits?
Exit door(s) on self-propelled medical units must meet the following requirements:Exit door(s) on self-propelled medical units must meet the following requirements:
(1) Exterior doors must be constructed for exterior use.(1) Exterior doors must be constructed for exterior use.
(2) The exterior door must be at least a twenty-eight inches wide clear opening by (2) The exterior door must be at least a twenty-eight inches wide clear opening by
seventy-two inches high.seventy-two inches high.
(3) Locks must be operable from the interior of the unit without use of a key.(3) Locks must be operable from the interior of the unit without use of a key.
(4) Exit doors may either be hinged or sliding. Roll-up doors may not be used to meet (4) Exit doors may either be hinged or sliding. Roll-up doors may not be used to meet
the requirements of this section.the requirements of this section.
(5) Exit doors where the threshold of the door is more than fourteen inches above the (5) Exit doors where the threshold of the door is more than fourteen inches above the
adjacent grade or road surface must have landings, stairs, handrail, and guardrails meeting adjacent grade or road surface must have landings, stairs, handrail, and guardrails meeting
the requirements of IBC chapter 10 as referenced in chapter the requirements of IBC chapter 10 as referenced in chapter 51-5051-50 WAC.WAC.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 12-15-061, § 296-150V-1185, filed 7/17/12, RCW. WSR 12-15-061, § 296-150V-1185, filed 7/17/12,
effective 9/1/12; WSR 99-18-069, § 296-150V-1185, filed 8/31/99, effective 10/1/99.]effective 9/1/12; WSR 99-18-069, § 296-150V-1185, filed 8/31/99, effective 10/1/99.]
296-150V-1190296-150V-1190
Interior privacy locks.Interior privacy locks.
If a conversion vendor unit or medical unit has an interior door, such as a bathroom If a conversion vendor unit or medical unit has an interior door, such as a bathroom
door, which has a privacy lock, the lock must contain an emergency release. The emergency door, which has a privacy lock, the lock must contain an emergency release. The emergency
release must be on the outside to permit entry when the door is locked from the inside.release must be on the outside to permit entry when the door is locked from the inside.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1190, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1190, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 2
5
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-1303296-150V-1303
How must storage batteries be installed in a conversion vendor unit or How must storage batteries be installed in a conversion vendor unit or
medical unit?medical unit?
Storage batteries subject to the provisions of this standard must be securely attached Storage batteries subject to the provisions of this standard must be securely attached
to the conversion vendor unit or medical unit. They must be installed in an area which is to the conversion vendor unit or medical unit. They must be installed in an area which is
vapor-tight to the interior and ventilated directly to the exterior of the unit. When batteries are vapor-tight to the interior and ventilated directly to the exterior of the unit. When batteries are
installed in a compartment, the compartment must be ventilated with openings of not less than installed in a compartment, the compartment must be ventilated with openings of not less than
two square inches at the top and two square inches at the bottom. Batteries must not be two square inches at the top and two square inches at the bottom. Batteries must not be
installed in a compartment containing spark or flame producing equipment, except in an installed in a compartment containing spark or flame producing equipment, except in an
engine generator compartment if the only charging source is the generator itself.engine generator compartment if the only charging source is the generator itself.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1303, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1303, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1330296-150V-1330
What are the mechanical requirements for a conversion vendor unit or What are the mechanical requirements for a conversion vendor unit or
medical unit?medical unit?
When mechanical and ventilation equipment is installed in or on a conversion vendor When mechanical and ventilation equipment is installed in or on a conversion vendor
unit or medical unit, it must be installed according to the requirements of the International unit or medical unit, it must be installed according to the requirements of the International
Mechanical Code, and to the conditions of the equipment approval or listing.Mechanical Code, and to the conditions of the equipment approval or listing.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 12-15-061, § 296-150V-1330, filed 7/17/12, RCW. WSR 12-15-061, § 296-150V-1330, filed 7/17/12,
effective 9/1/12; WSR 99-18-069, § 296-150V-1330, filed 8/31/99, effective 10/1/99.]effective 9/1/12; WSR 99-18-069, § 296-150V-1330, filed 8/31/99, effective 10/1/99.]
296-150V-1350296-150V-1350
What are the LPG system enclosure and mounting requirements for a What are the LPG system enclosure and mounting requirements for a
conversion vendor unit or medical unit?conversion vendor unit or medical unit?
(1) LPG containers must not be installed, nor stored temporarily, inside any unit. (1) LPG containers must not be installed, nor stored temporarily, inside any unit.
Exception: This prohibition does not apply to completely self-contained hand torches, lanterns, Exception: This prohibition does not apply to completely self-contained hand torches, lanterns,
or similar equipment with containers having a maximum water capacity of two and one-half or similar equipment with containers having a maximum water capacity of two and one-half
pounds (approximately one pound LPG capacity).pounds (approximately one pound LPG capacity).
(2) Containers, control valves and regulating equipment, when installed, must meet (2) Containers, control valves and regulating equipment, when installed, must meet
one of the following requirements:one of the following requirements:
(a) Be mounted on the "A" frame and not lower than the bottom of the trailer frame; or(a) Be mounted on the "A" frame and not lower than the bottom of the trailer frame; or
(b) Installed in a compartment that is vapor-tight to the inside of the conversion vendor (b) Installed in a compartment that is vapor-tight to the inside of the conversion vendor
unit or medical unit and accessible only from the outside; orunit or medical unit and accessible only from the outside; or
(c) Be mounted on the chassis or to the floor and neither the container nor its supports (c) Be mounted on the chassis or to the floor and neither the container nor its supports
may be lower than the top of the axle height.may be lower than the top of the axle height.
(3) The compartment must be ventilated at top and bottom to diffuse vapors. The (3) The compartment must be ventilated at top and bottom to diffuse vapors. The
compartment must be ventilated with two vents having an aggregate area of not less than two compartment must be ventilated with two vents having an aggregate area of not less than two
Page 2
6
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
percent of the floor area of the compartment and must open without restriction to the outside. percent of the floor area of the compartment and must open without restriction to the outside.
The required vents must be equally distributed between the floor and ceiling of the The required vents must be equally distributed between the floor and ceiling of the
compartment. If the lower vent is located in the access door or wall, the bottom edge of the compartment. If the lower vent is located in the access door or wall, the bottom edge of the
vent must be flush with the floor level of the compartment. The top vent must be located in the vent must be flush with the floor level of the compartment. The top vent must be located in the
access door or wall with the bottom of the vent not more than twelve inches below the ceiling access door or wall with the bottom of the vent not more than twelve inches below the ceiling
level of the compartment. All vents must have an unrestricted discharge to the outside level of the compartment. All vents must have an unrestricted discharge to the outside
atmosphere. Access doors or panels of compartments must not be equipped with locks or atmosphere. Access doors or panels of compartments must not be equipped with locks or
require special tools or knowledge to open.require special tools or knowledge to open.
(4) Doors, hoods, domes, or portions of housings and enclosures required to be (4) Doors, hoods, domes, or portions of housings and enclosures required to be
removed or opened for container replacement must incorporate means for clamping them removed or opened for container replacement must incorporate means for clamping them
firmly in place and preventing them from working loose during transit. Provisions must be firmly in place and preventing them from working loose during transit. Provisions must be
incorporated in the assembly to hold the containers firmly in position and prevent their incorporated in the assembly to hold the containers firmly in position and prevent their
movement during transit.movement during transit.
(5) LPG containers must be mounted on a substantial support or a base secured firmly (5) LPG containers must be mounted on a substantial support or a base secured firmly
to the conversion vendor unit or medical unit chassis. Neither the container nor its support can to the conversion vendor unit or medical unit chassis. Neither the container nor its support can
extend below the conversion vendor unit or medical unit frame.extend below the conversion vendor unit or medical unit frame.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1350, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1350, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1360296-150V-1360
What are the fuel gas piping design requirements for a conversion vendor What are the fuel gas piping design requirements for a conversion vendor
unit or medical unit?unit or medical unit?
Conversion vendor units or medical units requiring fuel gas for any purpose must be Conversion vendor units or medical units requiring fuel gas for any purpose must be
equipped with a gas piping system that is designed for LPG only or combination LPG and equipped with a gas piping system that is designed for LPG only or combination LPG and
natural gas.natural gas.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1360, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1360, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1380296-150V-1380
Can gas tubing be concealed in a conversion vendor unit or medical unit?Can gas tubing be concealed in a conversion vendor unit or medical unit?
(1) Tubing must not be run inside walls, floors, partitions, or roofs.(1) Tubing must not be run inside walls, floors, partitions, or roofs.
(2) If tubing passes through walls, floors, partitions, roofs, or similar installations, the (2) If tubing passes through walls, floors, partitions, roofs, or similar installations, the
tubing must be protected by the use of weather resistant grommets that snugly fit both the tubing must be protected by the use of weather resistant grommets that snugly fit both the
tubing and the hole through which the tubing passes.tubing and the hole through which the tubing passes.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1380, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1380, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 2
7
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-1390296-150V-1390
What are the pipe-joint compound requirements for gas piping in a What are the pipe-joint compound requirements for gas piping in a
conversion vendor unit or medical unit?conversion vendor unit or medical unit?
(1) Screw joints must be made tight with pipe-joint compound that is insoluble in (1) Screw joints must be made tight with pipe-joint compound that is insoluble in
liquefied petroleum gas.liquefied petroleum gas.
(2) Pipe-joint compound must be approved for the type of gas used. The pipe-joint (2) Pipe-joint compound must be approved for the type of gas used. The pipe-joint
compound must be applied to the male threads only.compound must be applied to the male threads only.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1390, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1390, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1400296-150V-1400
What are the gas piping hanger and support requirements for a conversion What are the gas piping hanger and support requirements for a conversion
vendor unit or medical unit?vendor unit or medical unit?
(1) All gas piping must be adequately supported by galvanized or equivalently (1) All gas piping must be adequately supported by galvanized or equivalently
protected metal straps or hangers at intervals of not more than 4 feet, except where adequate protected metal straps or hangers at intervals of not more than 4 feet, except where adequate
support and protection is provided by structural members.support and protection is provided by structural members.
(2) Gas pipe supply connections must be rigidly anchored to a structural member (2) Gas pipe supply connections must be rigidly anchored to a structural member
within 6 inches of the supply connections.within 6 inches of the supply connections.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1400, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1400, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1410296-150V-1410
What are the electrical bonding requirements for gas piping in a What are the electrical bonding requirements for gas piping in a
conversion vendor unit or medical unit?conversion vendor unit or medical unit?
(1) Gas piping must not be used for an electrical ground.(1) Gas piping must not be used for an electrical ground.
(2) The gas line must be bonded.(2) The gas line must be bonded.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1410, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1410, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1420296-150V-1420
How are gas supply connections in a conversion vendor unit or medical How are gas supply connections in a conversion vendor unit or medical
unit identified?unit identified?
Page 28 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
A label must be permanently attached on the outside of the exterior wall of the A label must be permanently attached on the outside of the exterior wall of the
conversion vendor unit or medical unit adjacent to the gas supply connection which provides conversion vendor unit or medical unit adjacent to the gas supply connection which provides
the following information:the following information:
(1) The type of system (i.e., liquid petroleum system or natural gas system or (1) The type of system (i.e., liquid petroleum system or natural gas system or
combination liquid petroleum and natural gas system);combination liquid petroleum and natural gas system);
(2) The appropriate Btuh input rating; and(2) The appropriate Btuh input rating; and
(3) If excess ("or more") Btuh input is allowed.(3) If excess ("or more") Btuh input is allowed.
(4) An example of a label would be: Natural Gas System, 250,000 Btuh or more.(4) An example of a label would be: Natural Gas System, 250,000 Btuh or more.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1420, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1420, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1430296-150V-1430
What requirements apply to gas piping system openings?What requirements apply to gas piping system openings?
All openings in the gas piping system must be closed gas-tight with threaded pipe All openings in the gas piping system must be closed gas-tight with threaded pipe
plugs or pipe caps.plugs or pipe caps.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1430, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1430, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1440296-150V-1440
Are gas piping shut-off valves required in a conversion vendor unit or Are gas piping shut-off valves required in a conversion vendor unit or
medical unit?medical unit?
(1) In addition to any valve on the appliance, a shut-off valve must be installed in the (1) In addition to any valve on the appliance, a shut-off valve must be installed in the
fuel piping outside of each gas appliance but inside the conversion vendor unit or medical unit fuel piping outside of each gas appliance but inside the conversion vendor unit or medical unit
structure and upstream of the union or connector. The shut-off valve must be located within structure and upstream of the union or connector. The shut-off valve must be located within
six feet of a cooking appliance and within three feet of any other appliance. A shut-off valve six feet of a cooking appliance and within three feet of any other appliance. A shut-off valve
may serve more than one appliance if located as required above.may serve more than one appliance if located as required above.
(2) Shut-off valves used in connection with gas piping must be of a type designed for (2) Shut-off valves used in connection with gas piping must be of a type designed for
use with liquefied petroleum gas. Shut-off valves must be tested and approved to ANSI use with liquefied petroleum gas. Shut-off valves must be tested and approved to ANSI
Z21.15 standard or equal.Z21.15 standard or equal.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1440, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1440, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1450296-150V-1450
What requirements apply to testing for gas piping leaks before conversion What requirements apply to testing for gas piping leaks before conversion
vendor unit or medical unit appliances are connected?vendor unit or medical unit appliances are connected?
Page 2
9
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
(1) The piping system must stand a pressure of at least 10 psi gauge for a period of (1) The piping system must stand a pressure of at least 10 psi gauge for a period of
not less than fifteen minutes without showing any drop in pressure.not less than fifteen minutes without showing any drop in pressure.
(2) Pressure must be measured with a gauge calibrated to be read in increments of not (2) Pressure must be measured with a gauge calibrated to be read in increments of not
greater than 1/10 pound.greater than 1/10 pound.
(3) The source of pressure must be isolated before the pressure tests are made. (3) The source of pressure must be isolated before the pressure tests are made.
Before a test is begun, the temperature of the ambient air and of the piping must be Before a test is begun, the temperature of the ambient air and of the piping must be
approximately the same, and constant air temperature must be maintained throughout the approximately the same, and constant air temperature must be maintained throughout the
test.test.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1450, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1450, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1460296-150V-1460
What requirements apply to testing for gas piping leaks after conversion What requirements apply to testing for gas piping leaks after conversion
vendor unit or medical unit appliances are connected?vendor unit or medical unit appliances are connected?
(1) After gas appliances have been connected, the gas-piping system must be (1) After gas appliances have been connected, the gas-piping system must be
subjected to a pressure test with the burner valves closed. The test consists of air at not less subjected to a pressure test with the burner valves closed. The test consists of air at not less
than ten inches nor more than fourteen inches pressure of water column (six to eight ounces). than ten inches nor more than fourteen inches pressure of water column (six to eight ounces).
The system must hold this pressure for a period of not less than ten minutes with no leakage. The system must hold this pressure for a period of not less than ten minutes with no leakage.
Before beginning the test, the temperature of the gas-piping system and the test air must be Before beginning the test, the temperature of the gas-piping system and the test air must be
equalized, and this shall be maintained throughout the test.equalized, and this shall be maintained throughout the test.
(2) Appliance shut-off valves ahead of gas cooking appliances may be closed for the (2) Appliance shut-off valves ahead of gas cooking appliances may be closed for the
performance of this test. When the test is satisfactorily performed, these valves must be performance of this test. When the test is satisfactorily performed, these valves must be
opened and, while the system is under pressure, the appliance connectors must be tested opened and, while the system is under pressure, the appliance connectors must be tested
with an approved leak detector or approved bubble solution.with an approved leak detector or approved bubble solution.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1460, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1460, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1470296-150V-1470
What are the requirements for appliance installations?What are the requirements for appliance installations?
(1) The installation of each appliance must conform to the manufacturer's installation (1) The installation of each appliance must conform to the manufacturer's installation
instructions. The manufacturer's instructions must be attached to the appliance.instructions. The manufacturer's instructions must be attached to the appliance.
(2) Combustion air inlets and flue gas outlets must be listed as components of the (2) Combustion air inlets and flue gas outlets must be listed as components of the
appliance and must be completely separated. The required separation may be obtained by:appliance and must be completely separated. The required separation may be obtained by:
(a) The installation of direct vent system (sealed combustion system) appliances; or(a) The installation of direct vent system (sealed combustion system) appliances; or
(b) The installation of appliances within enclosures so that the appliance combustion (b) The installation of appliances within enclosures so that the appliance combustion
system and venting system are separate from the interior atmosphere of the conversion system and venting system are separate from the interior atmosphere of the conversion
vendor unit or medical unit. There must not be any door, removable access panel, or other vendor unit or medical unit. There must not be any door, removable access panel, or other
opening into the enclosure from the inside of the conversion vendor unit or medical unit. Any opening into the enclosure from the inside of the conversion vendor unit or medical unit. Any
openings for ducts, piping, wiring, etc., must be sealed.openings for ducts, piping, wiring, etc., must be sealed.
(3) Ranges, cooktops, and ovens must not burn outside combustion air.(3) Ranges, cooktops, and ovens must not burn outside combustion air.
Page 30 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1470, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1470, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1530296-150V-1530
What general plumbing requirements apply?What general plumbing requirements apply?
This chapter also applies to the installation of plumbing equipment in any conversion This chapter also applies to the installation of plumbing equipment in any conversion
vendor unit or medical unit bearing or required to bear a department insignia. Plumbing vendor unit or medical unit bearing or required to bear a department insignia. Plumbing
fixtures, equipment, and installations in conversion vendor units and medical units must fixtures, equipment, and installations in conversion vendor units and medical units must
conform to the provisions of Chapter 7 of ANSI 119.2, 2002 edition or the Uniform Plumbing conform to the provisions of Chapter 7 of ANSI 119.2, 2002 edition or the Uniform Plumbing
Code and the amendments adopted by the State Building Code Council, except part 1, unless Code and the amendments adopted by the State Building Code Council, except part 1, unless
specifically exempted or required by this section. The following also apply:specifically exempted or required by this section. The following also apply:
(1) We will allow a 1-1/4 inch drain for handwashing sinks with an antisiphon vent.(1) We will allow a 1-1/4 inch drain for handwashing sinks with an antisiphon vent.
(2) An antisiphon vent will be allowed on one and two compartment sinks in units as (2) An antisiphon vent will be allowed on one and two compartment sinks in units as
long as there is one vent to the exterior so the system will function. Sinks with three or more long as there is one vent to the exterior so the system will function. Sinks with three or more
compartments must be installed as required by the Uniform Plumbing Code.compartments must be installed as required by the Uniform Plumbing Code.
[Statutory Authority: RCW [Statutory Authority: RCW 43.22.34043.22.340, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.48043.22.480, ,
and and 43.22.48543.22.485, 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RCW. WSR 03-12-044, § 296-150V-1530, filed RCW. WSR 03-12-044, § 296-150V-1530, filed
5/30/03, effective 6/30/03. Statutory Authority: Chapter 5/30/03, effective 6/30/03. Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-RCW. WSR 99-18-069, § 296-
150V-1530, filed 8/31/99, effective 10/1/99.]150V-1530, filed 8/31/99, effective 10/1/99.]
296-150V-1540296-150V-1540
What are the plumbing definitions?What are the plumbing definitions?
Definitions contained in the Uniform Plumbing Code apply to this chapter:Definitions contained in the Uniform Plumbing Code apply to this chapter:
"Drain outlet""Drain outlet" is the discharge end of the conversion vendor unit or medical unit main is the discharge end of the conversion vendor unit or medical unit main
drain to which a drain connector may be attached.drain to which a drain connector may be attached.
"Main drain""Main drain" is the principal artery of the conversion vendor unit or medical unit is the principal artery of the conversion vendor unit or medical unit
drainage system to which drainage branches may be connected.drainage system to which drainage branches may be connected.
"Water-supply connection""Water-supply connection" is the fitting or point of connection of the conversion is the fitting or point of connection of the conversion
vendor unit or medical unit water distribution system to a water connector.vendor unit or medical unit water distribution system to a water connector.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1540, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1540, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1550296-150V-1550
What requirements apply to drain outlets?What requirements apply to drain outlets?
Drain outlets must be equipped with a watertight cap or plug that must be permanently Drain outlets must be equipped with a watertight cap or plug that must be permanently
attached to the unit.attached to the unit.
Page 31 of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1550, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1550, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1560296-150V-1560
What is the minimum clearance for drain outlets?What is the minimum clearance for drain outlets?
The drain outlet and couplers must have a minimum clearance of three inches in any The drain outlet and couplers must have a minimum clearance of three inches in any
direction from all parts of the structure or appurtenances and with at least eighteen inches direction from all parts of the structure or appurtenances and with at least eighteen inches
unrestricted clearance directly in front of the drain outlet.unrestricted clearance directly in front of the drain outlet.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1560, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1560, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1570296-150V-1570
What requirements apply to water-supply connections?What requirements apply to water-supply connections?
Water-supply connections must be equipped with a watertight cap or plug that must be Water-supply connections must be equipped with a watertight cap or plug that must be
permanently attached to the vehicle.permanently attached to the vehicle.
Note
:
Note
:
The department of health may have more restrictive requirements. Before modifying your unit to comply with these The department of health may have more restrictive requirements. Before modifying your unit to comply with these
requirements, be sure to contact that agency
.
requirements, be sure to contact that agency
.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1570, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1570, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1580296-150V-1580
What requirements apply to water heater relief valves and safety devices?What requirements apply to water heater relief valves and safety devices?
(1) All water heaters must be installed with approved fully automatic valve or valves (1) All water heaters must be installed with approved fully automatic valve or valves
designed to provide temperature and pressure relief. Temperature and pressure relief valves designed to provide temperature and pressure relief. Temperature and pressure relief valves
must be tested and approved to ANSI Z21.22 standard or equal.must be tested and approved to ANSI Z21.22 standard or equal.
(2) Any temperature relief valve or combined pressure and temperature relief valve (2) Any temperature relief valve or combined pressure and temperature relief valve
installed for this purpose must have the temperature sensing element immersed in the hottest installed for this purpose must have the temperature sensing element immersed in the hottest
water within the upper six inches of the tank. It must be set to start relieving at a pressure of water within the upper six inches of the tank. It must be set to start relieving at a pressure of
150 psi or the rated working pressure of the tank, whichever is lower, and at or below a water 150 psi or the rated working pressure of the tank, whichever is lower, and at or below a water
temperature of 210 degrees Fahrenheit.temperature of 210 degrees Fahrenheit.
(3) Relief valves must be provided with full-sized drains. Drains must be directed to the (3) Relief valves must be provided with full-sized drains. Drains must be directed to the
exterior of the unit, exiting at least six inches above the ground, and must exhaust downward. exterior of the unit, exiting at least six inches above the ground, and must exhaust downward.
Drain lines must be of a material approved for hot water distribution and must drain fully by Drain lines must be of a material approved for hot water distribution and must drain fully by
gravity, must not be trapped, and must not have their outlets threaded.gravity, must not be trapped, and must not have their outlets threaded.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1580, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1580, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
Page 3
2
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-1590296-150V-1590
What requirements apply to waste holding tanks for conversion vendor What requirements apply to waste holding tanks for conversion vendor
units?units?
Conversion vendor units may use either portable waste holding tanks approved by the Conversion vendor units may use either portable waste holding tanks approved by the
department of health or permanently mounted waste holding tanks.department of health or permanently mounted waste holding tanks.
(1) All portable waste holding tanks must be listed for the intended use and used per (1) All portable waste holding tanks must be listed for the intended use and used per
their listing.their listing.
(2) All permanently mounted waste holding tanks must meet the following (2) All permanently mounted waste holding tanks must meet the following
specifications:specifications:
(a) Tanks must be listed for the intended use, installed per their listing, and be securely (a) Tanks must be listed for the intended use, installed per their listing, and be securely
installed to prevent displacement during transportation;installed to prevent displacement during transportation;
(b) Tanks must be easily removable for service, repair or replacement without having (b) Tanks must be easily removable for service, repair or replacement without having
to remove any permanent construction;to remove any permanent construction;
(c) Neither the inlet nor vent fitting may extend downward into the tank more than 1-1/2 (c) Neither the inlet nor vent fitting may extend downward into the tank more than 1-1/2
inches;inches;
(d) The drain opening must be located at the lowest point of the tank;(d) The drain opening must be located at the lowest point of the tank;
(e) Tanks must be vented at the highest point in the top of the tank by one of the (e) Tanks must be vented at the highest point in the top of the tank by one of the
following methods:following methods:
(i) A 1-1/4 inch diameter vent pipe;(i) A 1-1/4 inch diameter vent pipe;
(ii) A continuous vent serving as a drain from one additional fixture provided the drain (ii) A continuous vent serving as a drain from one additional fixture provided the drain
portion is increased one pipe size larger than the connected trap arm;portion is increased one pipe size larger than the connected trap arm;
(iii) Two or more vented drains when at least one is wet-vented and each drain is (iii) Two or more vented drains when at least one is wet-vented and each drain is
separately connected to the top of the tank;separately connected to the top of the tank;
(f) A fullway termination valve must be installed in the tank; and(f) A fullway termination valve must be installed in the tank; and
(g) No drain connection may be made between liquid and body waste holding tanks (g) No drain connection may be made between liquid and body waste holding tanks
upstream of fullway termination valves.upstream of fullway termination valves.
[Statutory Authority: Chapter [Statutory Authority: Chapter 43.2243.22 RCW. WSR 99-18-069, § 296-150V-1590, filed 8/31/99, RCW. WSR 99-18-069, § 296-150V-1590, filed 8/31/99,
effective 10/1/99.]effective 10/1/99.]
296-150V-1600296-150V-1600
What are the requirements associated with medical and conversion What are the requirements associated with medical and conversion
vending units that have been manufactured and used outside the state vending units that have been manufactured and used outside the state
according to RCW according to RCW 43.22.38043.22.380??
(1) If the unit does not have any alterations made to body and frame design, (1) If the unit does not have any alterations made to body and frame design,
construction, plumbing, heating or electrical installations since it was constructed, it will need construction, plumbing, heating or electrical installations since it was constructed, it will need
an insignia issued by the department. In order to receive the insignia, the unit must have an insignia issued by the department. In order to receive the insignia, the unit must have
been:been:
(a) Manufactured outside the state of Washington. Proof of this must be demonstrated (a) Manufactured outside the state of Washington. Proof of this must be demonstrated
by a certificate of origin, bill of sale, proof of purchase of materials, manufacture identification by a certificate of origin, bill of sale, proof of purchase of materials, manufacture identification
Page 3
3
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
tag or serial number, or any other means acceptable to the department that shows that the tag or serial number, or any other means acceptable to the department that shows that the
unit was manufactured outside the state.unit was manufactured outside the state.
(b) Used outside the state for at least six months or more. Proof of this must be (b) Used outside the state for at least six months or more. Proof of this must be
demonstrated by showing the purchase of a license plate, a permit(s) issued by another state demonstrated by showing the purchase of a license plate, a permit(s) issued by another state
agency for use in another state, insurance certificate, bill of sale, or any other means agency for use in another state, insurance certificate, bill of sale, or any other means
acceptable to the department that shows that the unit was used outside the state for at least acceptable to the department that shows that the unit was used outside the state for at least
six months.six months.
(2) If the unit has had alterations made to the body and frame design, construction, (2) If the unit has had alterations made to the body and frame design, construction,
plumbing, heating or electrical installations since it was constructed, it will need an insignia plumbing, heating or electrical installations since it was constructed, it will need an insignia
issued by the department. In order to receive the insignia, the alterations to the unit must be issued by the department. In order to receive the insignia, the alterations to the unit must be
inspected and approved by the department and the unit must have been:inspected and approved by the department and the unit must have been:
(a) Manufactured outside the state of Washington. Proof of this must be demonstrated (a) Manufactured outside the state of Washington. Proof of this must be demonstrated
by a certificate of origin, bill of sale, proof of purchase of materials, manufacture identification by a certificate of origin, bill of sale, proof of purchase of materials, manufacture identification
tag or serial number, or any other means acceptable to the department that shows that the tag or serial number, or any other means acceptable to the department that shows that the
unit was manufactured outside the state.unit was manufactured outside the state.
(b) Used outside the state for at least six months or more. Proof of this must be (b) Used outside the state for at least six months or more. Proof of this must be
demonstrated by showing the purchase of a license plate, a permit(s) issued by another state demonstrated by showing the purchase of a license plate, a permit(s) issued by another state
agency for use in another state, insurance certificate, bill of sale, or any other means agency for use in another state, insurance certificate, bill of sale, or any other means
acceptable to the department that shows that the unit was used outside the state for at least acceptable to the department that shows that the unit was used outside the state for at least
six months.six months.
[Statutory Authority: RCW [Statutory Authority: RCW 43.22.34043.22.340, , 43.22.40043.22.400, , 43.22.43243.22.432, , 43.22.43343.22.433, , 43.22.43443.22.434, , 43.22.48043.22.480, ,
and and 43.22.48543.22.485, 2002 c 268, and chapter , 2002 c 268, and chapter 43.2243.22 RCW. WSR 03-12-044, § 296-150V-1600, filed RCW. WSR 03-12-044, § 296-150V-1600, filed
5/30/03, effective 6/30/03.]5/30/03, effective 6/30/03.]
296-150V-3000296-150V-3000
Conversion vendor units and medical units—Fees.Conversion vendor units and medical units—Fees.
INITIAL FILING FEEINITIAL FILING FEE $39.10$39.10
DESIGN PLAN FEES:DESIGN PLAN FEES:
INITIAL FEE - MASTER DESIGNINITIAL FEE - MASTER DESIGN $270.90$270.90
INITIAL FEE - ONE YEAR DESIGNINITIAL FEE - ONE YEAR DESIGN $110.70$110.70
RENEWAL FEERENEWAL FEE $47.00$47.00
RESUBMIT FEERESUBMIT FEE $79.00$79.00
ADDENDUM (Approval expires on same date as original plan)ADDENDUM (Approval expires on same date as original plan) $79.00$79.00
ELECTRONIC PLAN SUBMITTAL FEE $5.50 per page for the first set of plans and ELECTRONIC PLAN SUBMITTAL FEE $5.50 per page for the first set of plans and
$1.00 per page for each additional set of plans. These fees are in addition to any $1.00 per page for each additional set of plans. These fees are in addition to any
applicable design plan fees required under this section.applicable design plan fees required under this section.
ELECTRICAL PLAN REVIEWELECTRICAL PLAN REVIEW - For medical units, find fees at - For medical units, find fees at
http://apps.leg.wa.gov/wac/default.aspx?cite= http://apps.leg.wa.gov/wac/default.aspx?cite= 296-46B-906296-46B-906
RECIPROCAL PLAN REVIEW:RECIPROCAL PLAN REVIEW:
INITIAL FEE - MASTER DESIGNINITIAL FEE - MASTER DESIGN $120.70$120.70
INITIAL FEE - ONE YEAR DESIGNINITIAL FEE - ONE YEAR DESIGN $72.90$72.90
RENEWAL FEERENEWAL FEE $72.90$72.90
ADDENDUMADDENDUM $72.90$72.90
Page 3
4
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
APPROVAL OF EACH SET OF DESIGN PLANS BEYOND FIRST TWO SETSAPPROVAL OF EACH SET OF DESIGN PLANS BEYOND FIRST TWO SETS $14.60$14.60
DEPARTMENT INSPECTION FEES:DEPARTMENT INSPECTION FEES:
INSPECTION/REINSPECTION (Per hour* plus travel time* and mileage**)INSPECTION/REINSPECTION (Per hour* plus travel time* and mileage**) $79.00$79.00
TRAVEL (Per hour)*TRAVEL (Per hour)* $79.00$79.00
PER DIEM**PER DIEM**
HOTEL***HOTEL***
MILEAGE**MILEAGE**
RENTAL CAR***RENTAL CAR***
PARKING***PARKING***
AIRFARE***AIRFARE***
ALTERATION INSPECTION (One hour plus insignia alteration fee)ALTERATION INSPECTION (One hour plus insignia alteration fee) $118.30$118.30
INSIGNIA FEES:INSIGNIA FEES:
FIRST SECTION/ALTERATIONFIRST SECTION/ALTERATION $22.70$22.70
REISSUED-LOST/DAMAGEDREISSUED-LOST/DAMAGED $14.60$14.60
EXEMPTEXEMPT $39.10$39.10
OTHER FEES:OTHER FEES:
FIELD TECHNICAL SERVICE (Per hour* plus travel time* and mileage**)FIELD TECHNICAL SERVICE (Per hour* plus travel time* and mileage**) $79.00$79.00
PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (One free PUBLICATION PRINTING AND DISTRIBUTION OF RCWs AND WACs (One free
copy per year upon request)copy per year upon request)
$14.60$14.60
REFUND FEEREFUND FEE $26.00$26.00
** Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.Minimum charge of 1 hour; time spent greater than 1 hour is charged in 1/2 hour increments.
**** Per state guidelines.Per state guidelines.
******
A
ctual charges incurred
.A
ctual charges incurred
.
[Statutory Authority: Chapters [Statutory Authority: Chapters 18.2718.27, 70.87, 43.22, and , 70.87, 43.22, and 43.22A43.22A RCW. WSR 18-24-102, § 296-RCW. WSR 18-24-102, § 296-
150V-3000, filed 12/4/18, effective 1/4/19. Statutory Authority: Chapter 150V-3000, filed 12/4/18, effective 1/4/19. Statutory Authority: Chapter 43.2243.22 RCW and 2011 RCW and 2011
1st sp.s. c 50. WSR 12-06-069, § 296-150V-3000, filed 3/6/12, effective 4/30/12. Statutory 1st sp.s. c 50. WSR 12-06-069, § 296-150V-3000, filed 3/6/12, effective 4/30/12. Statutory
Authority: Chapters Authority: Chapters 18.10618.106, , 43.2243.22 RCW, 2008 c 285 and c 329. WSR 08-12-042, § 296-150V-RCW, 2008 c 285 and c 329. WSR 08-12-042, § 296-150V-
3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 3000, filed 5/30/08, effective 6/30/08. Statutory Authority: Chapters 18.2718.27, 18.106, 43.22, and , 18.106, 43.22, and
70.8770.87 RCW. WSR 07-11-128, § 296-150V-3000, filed 5/22/07, effective 6/30/07. Statutory RCW. WSR 07-11-128, § 296-150V-3000, filed 5/22/07, effective 6/30/07. Statutory
Authority: Chapters Authority: Chapters 18.10618.106, 43.22, and , 43.22, and 70.8770.87 RCW. WSR 06-10-066, § 296-150V-3000, filed RCW. WSR 06-10-066, § 296-150V-3000, filed
5/2/06, effective 6/30/06. Statutory Authority: Chapter 5/2/06, effective 6/30/06. Statutory Authority: Chapter 43.2243.22 RCW. WSR 05-23-002, § 296-RCW. WSR 05-23-002, § 296-
150V-3000, filed 11/3/05, effective 12/4/05. Statutory Authority: Chapters 150V-3000, filed 11/3/05, effective 12/4/05. Statutory Authority: Chapters 18.2718.27, 43.22, and , 43.22, and
70.8770.87 RCW. WSR 05-12-032, § 296-150V-3000, filed 5/24/05, effective 6/30/05. Statutory RCW. WSR 05-12-032, § 296-150V-3000, filed 5/24/05, effective 6/30/05. Statutory
Authority: Chapter Authority: Chapter 43.2243.22 RCW and 2003 c 291. WSR 05-01-102, § 296-150V-3000, filed RCW and 2003 c 291. WSR 05-01-102, § 296-150V-3000, filed
12/14/04, effective 2/1/05. Statutory Authority: Chapters 12/14/04, effective 2/1/05. Statutory Authority: Chapters 18.2718.27 and and 43.2243.22 RCW. WSR 04-12-RCW. WSR 04-12-
048, § 296-150V-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 048, § 296-150V-3000, filed 5/28/04, effective 6/30/04. Statutory Authority: RCW 43.22.35043.22.350, ,
43.22.43443.22.434, , 43.22.48043.22.480, , 43.22.50043.22.500, , 70.87.03070.87.030, , 18.106.07018.106.070, , 18.106.12518.106.125, 2001 c 7, and chapters , 2001 c 7, and chapters
18.10618.106, 43.22, and , 43.22, and 70.8770.87 RCW. WSR 03-12-045, § 296-150V-3000, filed 5/30/03, effective RCW. WSR 03-12-045, § 296-150V-3000, filed 5/30/03, effective
6/30/03. Statutory Authority: RCW 6/30/03. Statutory Authority: RCW 43.22.35043.22.350, , 43.22.43443.22.434, , 43.22.48043.22.480, , 43.22.50043.22.500, , 18.27.04018.27.040,
,
18.27.07018.27.070, , 18.27.07518.27.075, , 70.87.03070.87.030, , 19.28.04119.28.041, , 19.28.05119.28.051, , 19.28.10119.28.101, , 19.28.12119.28.121, , 19.28.16119.28.161, ,
19.28.20119.28.201, , 19.28.21119.28.211, , 19.28.34119.28.341, 2001 c 7, 2002 c 249, and chapters , 2001 c 7, 2002 c 249, and chapters 19.2819.28, 43.22, 18.27, , 43.22, 18.27,
and and 70.8770.87 RCW. WSR 02-12-022, § 296-150V-3000, filed 5/28/02, effective 6/28/02. Statutory RCW. WSR 02-12-022, § 296-150V-3000, filed 5/28/02, effective 6/28/02. Statutory
Authority: RCW Authority: RCW 43.22.35043.22.350, , 43.22.43443.22.434, , 43.22.48043.22.480, , 43.22.50043.22.500, , 18.27.07018.27.070, , 18.27.07518.27.075, ,
70.87.03070.87.030, , 19.28.04119.28.041, , 19.28.05119.28.051, , 19.28.10119.28.101, , 19.28.12119.28.121, , 19.28.16119.28.161, , 19.28.20119.28.201, , 19.28.21119.28.211, ,
19.28.34119.28.341, 2001 c 159, and chapters , 2001 c 159, and chapters 43.2243.22, 19.28, 18.27, and , 19.28, 18.27, and 70.8770.87 RCW. WSR 01-12-035, § RCW. WSR 01-12-035, §
Page 3
5
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e
296-150V-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: Chapter 296-150V-3000, filed 5/29/01, effective 6/29/01. Statutory Authority: Chapter 43.2243.22 RCW. RCW.
WSR 99-18-069, § 296-150V-3000, filed 8/31/99, effective 10/1/99.]WSR 99-18-069, § 296-150V-3000, filed 8/31/99, effective 10/1/99.]
Page 3
6
of 3
6
Chapter 29
6
-150V WAC:
2
/
22
/
201
9
https://apps.leg.wa.gov/wac/default.aspx?cite=29
-150V&full=tru
e